EmissionsLookup
Clean Water Act

AUTUMN RIDGE

Quick Summary

  • Assessed $0 in total penalties since records began.
Address
NEW TEXAS ROAD AT MALLISE LANE
PLUM, BOROUGH OF, PA 15239
View on map ↗
County
ALLEGHENY County
Industry
Construction
NAICS (North American Industry Classification)
236117
Total Penalties
$0
Registry ID
110070053825

Compliance Violations

Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.

Program Type Violation Date Return to Compliance Status
cwa WW Storm Water Construction - Failure to properly operate and maintain BMPs Sep 14, 2021 Open
cwa WW Storm Water Construction - Failure to properly install/implement BMPs Sep 14, 2021 Open
cwa WW Storm Water Construction - Narrative effluent violation Sep 14, 2021 Open
cwa WW Storm Water Construction - Failure to properly operate and maintain BMPs Jul 27, 2021 Open
cwa WW Storm Water Construction - Narrative effluent violation Jul 27, 2021 Open
cwa WW Storm Water Construction - Failure to submit required report (non-DMR) Dec 9, 2020 Open
cwa WW Storm Water Construction - Narrative effluent violation Dec 9, 2020 Open
cwa WW Storm Water Construction - Failure to properly install/implement BMPs Dec 9, 2020 Open
cwa WW Storm Water Construction - Failure to properly install/implement BMPs Jul 21, 2020 Open
cwa WW Storm Water Construction - Narrative effluent violation Jul 21, 2020 Open
cwa WW Storm Water Construction - Failure to submit required report (non-DMR) Jul 21, 2020 Open
cwa WW Storm Water Construction - Narrative effluent violation Mar 10, 2020 Open
cwa WW Storm Water Construction - Failure to submit required report (non-DMR) Mar 10, 2020 Open
cwa WW Storm Water Construction - Failure to properly install/implement BMPs Mar 10, 2020 Open
cwa WW Storm Water Construction - Failure to properly operate and maintain BMPs Mar 10, 2020 Open
cwa WW Storm Water Construction - Failure to Implement SWPPP/SWMP Mar 10, 2020 Open
cwa WW Storm Water Construction - Failure to properly operate and maintain BMPs Feb 4, 2020 Open
cwa WW Storm Water Construction - Narrative effluent violation Feb 4, 2020 Open
cwa WW Storm Water Construction - Failure to submit required report (non-DMR) Feb 4, 2020 Open
cwa WW Storm Water Construction - Failure to properly install/implement BMPs Feb 4, 2020 Open
cwa WW Storm Water Construction - Failure to properly install/implement BMPs Jan 3, 2020 Open
cwa WW Storm Water Construction - Narrative effluent violation Jan 3, 2020 Open
cwa WW Storm Water Construction - Failure to submit required report (non-DMR) Jan 3, 2020 Open
cwa WW Storm Water Construction - Failure to Implement SWPPP/SWMP Jan 3, 2020 Open
cwa WW Storm Water Construction - Narrative effluent violation Nov 26, 2019 Open
cwa WW Storm Water Construction - Failure to Implement SWPPP/SWMP Nov 26, 2019 Open
cwa WW Storm Water Construction - Failure to properly operate and maintain BMPs Nov 26, 2019 Open
cwa WW Storm Water Construction - Failure to properly install/implement BMPs Nov 26, 2019 Open
cwa WW Storm Water Construction - Failure to submit required report (non-DMR) Nov 26, 2019 Open
cwa WW Storm Water Construction - Narrative effluent violation Sep 13, 2019 Open
cwa WW Storm Water Construction - Failure to submit required report (non-DMR) Sep 13, 2019 Open
cwa WW Storm Water Construction - Violation of a milestone in an order Sep 13, 2019 Open
cwa WW Storm Water Construction - Failure to properly operate and maintain BMPs Sep 13, 2019 Open
cwa WW Storm Water Construction - Failure to Implement SWPPP/SWMP Sep 13, 2019 Open
cwa WW Storm Water Construction - Failure to Implement SWPPP/SWMP Aug 16, 2019 Open
cwa WW Storm Water Construction - Failure to properly operate and maintain BMPs Aug 16, 2019 Open
cwa WW Storm Water Construction - Narrative effluent violation Aug 16, 2019 Open
cwa WW Storm Water Construction - Failure to properly install/implement BMPs Aug 16, 2019 Open
cwa WW Storm Water Construction - Failure to submit required report (non-DMR) Aug 16, 2019 Open
cwa WW Storm Water Construction - Violation of a milestone in an order Aug 16, 2019 Open
cwa WW Storm Water Construction - Narrative effluent violation Apr 24, 2019 Open
cwa WW Storm Water Construction - Failure to properly operate and maintain BMPs Apr 24, 2019 Open
cwa WW Storm Water Construction - Failure to properly operate and maintain BMPs Apr 4, 2019 Open
cwa WW Storm Water Construction - Narrative effluent violation Apr 4, 2019 Open
cwa WW Storm Water Construction - Failure to properly install/implement BMPs Apr 4, 2019 Open
cwa WW Storm Water Construction - Failure to Implement SWPPP/SWMP Apr 4, 2019 Open
cwa WW Storm Water Construction - Failure to properly install/implement BMPs Jan 28, 2019 Open
cwa WW Storm Water Construction - Failure to Maintain Records Jan 28, 2019 Open
cwa WW Storm Water Construction - Failure to properly operate and maintain BMPs Jan 28, 2019 Open

Other facilities in ALLEGHENY County, PA

MID-CONTINENT COAL & COKE CO/CLAIRTON SCREENING PLT
_CLAIRTON, PA · Wholesale Trade
WHEMCO STEEL CASTINGS INC/WEST HOMESTEAD
HOMESTEAD, PA · Manufacturing
DEEP VLY LDFL
OAKDALE, PA
INDUSTRIAL SCIENTIFIC CORP
OAKDALE, PA · Retail Trade
All facilities in PA →