PROCTOR WASTEWATER TREATMENT FACILITY
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
29 PATCH STREET
PROCTOR, VT 05765
View on map ↗ - County
- RUTLAND County
- Industry
- Utilities
- NAICS (North American Industry Classification)
- 221320
- Inspections
- 3 · last Jul 20, 2023
- Total Penalties
- $0
- Registry ID
- 110010911095
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event reported late | Dec 31, 2025 | — | Open |
| cwa | Schedule Event unachieved and not reported | Dec 31, 2025 | Jan 31, 2026 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jul 31, 2025 | Aug 31, 2025 | Resolved |
| cwa | Schedule Event reported late | Dec 31, 2024 | — | Open |
| cwa | Schedule Event unachieved but reported | Jul 31, 2024 | Feb 7, 2025 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jul 31, 2024 | Feb 7, 2025 | Resolved |
| cwa | Schedule Event reported late | Jul 31, 2024 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 31, 2024 | — | Open |
| cwa | Schedule Event unachieved and not reported | Dec 31, 2023 | Jan 31, 2024 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jun 30, 2023 | Oct 30, 2024 | Resolved |
| cwa | Schedule Event reported late | Jun 30, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Jun 30, 2023 | — | Open |
| cwa | Schedule Event unachieved but reported | Jun 30, 2023 | Oct 30, 2024 | Resolved |
| cwa | Schedule Event unachieved and not reported | Dec 31, 2020 | Jul 17, 2021 | Resolved |
| cwa | Schedule Event reported late | Dec 31, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Dec 31, 2020 | — | Open |
| cwa | Schedule Event unachieved but reported | Dec 31, 2020 | Jun 10, 2021 | Resolved |
| cwa | Schedule Event reported late | Dec 31, 2019 | — | Open |
| cwa | Schedule Event unachieved and not reported | Dec 31, 2016 | Jan 31, 2017 | Resolved |
| cwa | Schedule Event unachieved and not reported | Dec 31, 2015 | Jan 31, 2016 | Resolved |
| cwa | Schedule Event reported late | Dec 31, 2014 | — | Open |
| cwa | Schedule Event reported late | Dec 31, 2013 | — | Open |
| cwa | WW SSO - Discharge to Waters | Jun 23, 2013 | Jun 23, 2013 | Resolved |
| cwa | Schedule Event reported late | Dec 31, 2012 | — | Open |
| cwa | Schedule Event reported late | Dec 31, 2011 | — | Open |
| cwa | Schedule Event reported late | Dec 31, 2009 | — | Open |
| cwa | Schedule Event achieved late but reported | Dec 31, 2009 | — | Open |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 76.00 % | 85.00 | +60% | Jun 2025 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 60.00 % | 85.00 | +167% | May 2025 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 81.00 % | 85.00 | +27% | Apr 2025 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 0.91 mg/L | 0.80 | +14% | May 2024 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 70.00 % | 85.00 | +100% | May 2024 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 69.00 % | 85.00 | +107% | Apr 2024 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 70.00 % | 85.00 | +100% | Apr 2024 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 73.07 % | 85.00 | +80% | Mar 2024 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 0.99 mg/L | 0.80 | +24% | Mar 2024 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 48.07 % | 85.00 | +246% | Mar 2024 | Open |
| E. coli, thermotol, MF, MTEC | DMR, Limited - Numeric Violation | 200.00 MPN/100mL | 77.00 | +160% | Jan 2024 | Open |
| E. coli, thermotol, MF, MTEC | DMR, Limited - Numeric Violation | 170.00 MPN/100mL | 77.00 | +121% | Dec 2023 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 84.00 % | 85.00 | +7% | Dec 2023 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 46.00 mg/L | 45.00 | +2% | Oct 2023 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 46.00 mg/L | 45.00 | +2% | Oct 2023 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 69.00 % | 85.00 | +107% | Oct 2023 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 79.00 % | 85.00 | +40% | Jun 2023 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 0.94 mg/L | 0.80 | +18% | May 2023 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 64.00 % | 85.00 | +140% | May 2023 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 77.00 % | 85.00 | +53% | Mar 2023 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 0.84 mg/L | 0.80 | +5% | Mar 2023 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 71.00 % | 85.00 | +93% | Mar 2023 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 77.00 % | 85.00 | +53% | Feb 2023 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 83.00 % | 85.00 | +13% | Sep 2022 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.00 mg/L | 0.80 | +25% | May 2022 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.35 MGD | 0.33 | +9% | May 2022 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.39 MGD | 0.33 | +20% | Apr 2022 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 83.00 % | 85.00 | +13% | Mar 2021 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 77.00 % | 85.00 | +53% | Apr 2020 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.33 MGD | 0.33 | +2% | Apr 2020 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 63.00 % | 85.00 | +147% | Apr 2020 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.34 MGD | 0.33 | +5% | Mar 2020 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 58.11 kg/d | 55.39 | +5% | Mar 2020 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 84.00 % | 85.00 | +7% | Mar 2020 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 81.27 kg/d | 55.39 | +47% | Mar 2020 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 0.86 mg/L | 0.80 | +8% | Jan 2020 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 82.00 % | 85.00 | +20% | Jan 2020 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 0.98 mg/L | 0.80 | +23% | Dec 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.45 MGD | 0.33 | +39% | May 2019 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 84.00 % | 85.00 | +7% | May 2019 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 84.00 % | 85.00 | +7% | May 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.54 MGD | 0.33 | +66% | Apr 2019 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 77.00 % | 85.00 | +53% | Apr 2019 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 74.00 % | 85.00 | +73% | May 2018 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.34 MGD | 0.33 | +4% | Apr 2018 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 0.83 mg/L | 0.80 | +4% | Feb 2018 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.01 mg/L | 0.80 | +26% | Dec 2017 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 82.00 % | 85.00 | +20% | Jul 2017 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 52.21 kg/d | 36.91 | +41% | Jun 2017 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 33.20 mg/L | 30.00 | +11% | Jun 2017 | Open |
Enforcement Actions
Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.