Non-Compliance
Clean Water Act
MORGAN CITY OF - MUNICIPAL SEPARATE STORM SEWER SYSTEM
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
CITYWIDE STORM SEWER SYSTEM
MORGAN CITY, LA 70000
View on map ↗ - County
- ST. MARY County
- Inspections
- 1 · last Mar 6, 2023
- Total Penalties
- $0 · last Nov 26, 2013
- Registry ID
- 110015605442
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
4
Water (CWA)
Qtrs Non-Compliant
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event unachieved and not reported | Mar 10, 2025 | Apr 10, 2025 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 10, 2024 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 10, 2024 | Jun 11, 2024 | Resolved |
| cwa | Schedule Event reported late | Mar 10, 2024 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 10, 2024 | Jun 11, 2024 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 10, 2023 | Jun 20, 2023 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 10, 2023 | Jun 20, 2023 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 10, 2023 | — | Open |
| cwa | Schedule Event reported late | Mar 10, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 10, 2022 | — | Open |
| cwa | Schedule Event reported late | Mar 10, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 10, 2022 | Jul 10, 2023 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 10, 2022 | Jul 10, 2023 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 10, 2021 | — | Open |
| cwa | Schedule Event reported late | Mar 10, 2021 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 10, 2021 | Sep 13, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 10, 2021 | Sep 13, 2021 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 10, 2019 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 10, 2019 | May 28, 2019 | Resolved |
| cwa | Schedule Event reported late | Mar 10, 2019 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 10, 2019 | May 28, 2019 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 10, 2014 | — | Open |
| cwa | Schedule Event reported late | Mar 10, 2014 | — | Open |
| cwa | WW Storm Water MS4 - Failure to Implement SWPPP/SWMP | Jun 26, 2013 | Feb 7, 2014 | Resolved |
| cwa | WW Storm Water MS4 - Failure to develop any or adequate SWPPP/SWMP | Jun 26, 2013 | Feb 7, 2014 | Resolved |
| cwa | WW Storm Water MS4 - Failure to submit required report (non-DMR) | Dec 31, 2012 | Feb 7, 2014 | Resolved |
| cwa | WW Storm Water MS4 - Failure to submit required report (non-DMR) | Dec 31, 2011 | Feb 7, 2014 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 10, 2011 | Feb 7, 2014 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 10, 2010 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 10, 2010 | Jul 16, 2010 | Resolved |
| cwa | Schedule Event reported late | Mar 10, 2010 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 10, 2010 | May 24, 2010 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 10, 2009 | Aug 26, 2009 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 10, 2009 | — | Open |
| cwa | Schedule Event reported late | Mar 10, 2009 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 10, 2009 | Aug 27, 2009 | Resolved |
| cwa | Effluent Violations - Numeric effluent violation | Jun 12, 2006 | Jan 8, 2007 | Resolved |
Enforcement Actions
Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.
State Administrative Order of Consent
Clean Water Act
· Case LA-WEXP1300638 · Nov 26, 2013
$1,400
State Administrative Order of Consent
Clean Water Act
· Case LA-N00015160 · Jul 12, 2006
$300
Other facilities in ST. MARY County, LA
PERDIDO ENERGY LOUISIANA, LLC
GORDY, LA
TRI-STAR OPCO LLC - COTE BLANCHE ISLAND TANK BATTERY #1
CYPREMORT, LA
CHITIMACHA TRIBE OF LOUISIANA
CHARENTON, LA
SMI COMPANIES, INC.
FRANKLIN, LA