- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $5,600 in total penalties since records began.
- Address
-
3467 STATE RTE 7
HOOSICK FALLS, NY 12090
View on map ↗ - County
- RENSSELAER County
- Total Penalties
- $5,600 · last Jan 9, 2025
- Registry ID
- 110064247701
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event unachieved and not reported | Jan 28, 2023 | Jan 9, 2025 | Resolved |
| cwa | Schedule Event unachieved but reported | Jan 28, 2021 | May 27, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jan 28, 2021 | May 27, 2021 | Resolved |
| cwa | Schedule Event reported late | Jan 28, 2021 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 28, 2021 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jan 28, 2020 | Feb 28, 2020 | Resolved |
| cwa | Schedule Event reported late | Mar 1, 2019 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 1, 2019 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 1, 2019 | Jul 11, 2025 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 1, 2019 | Jul 11, 2025 | Resolved |
| cwa | WW Storm Water Non-Construction - CWA §308 Failure to submit required permit application info | Sep 26, 2018 | Jul 11, 2025 | Resolved |
| cwa | WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP | Sep 26, 2018 | Jul 11, 2025 | Resolved |
| cwa | Schedule Event reported late | Feb 28, 2017 | — | Open |
| cwa | Schedule Event unachieved but reported | Feb 28, 2017 | Feb 6, 2018 | Resolved |
| cwa | Schedule Event achieved late but reported | Feb 28, 2017 | — | Open |
| cwa | Schedule Event unachieved and not reported | Feb 28, 2017 | Feb 6, 2018 | Resolved |
| cwa | Schedule Event achieved late but reported | Feb 29, 2016 | — | Open |
| cwa | Schedule Event unachieved and not reported | Feb 29, 2016 | Feb 1, 2017 | Resolved |
| cwa | Schedule Event unachieved but reported | Feb 29, 2016 | Feb 1, 2017 | Resolved |
| cwa | Schedule Event reported late | Feb 29, 2016 | — | Open |
| cwa | Schedule Event achieved late but reported | Feb 28, 2015 | — | Open |
| cwa | Schedule Event unachieved and not reported | Feb 28, 2015 | Dec 14, 2015 | Resolved |
| cwa | Schedule Event reported late | Feb 28, 2015 | — | Open |
| cwa | Schedule Event unachieved but reported | Feb 28, 2015 | Dec 14, 2015 | Resolved |
| cwa | Schedule Event unachieved and not reported | Feb 28, 2014 | May 12, 2015 | Resolved |
| cwa | Schedule Event unachieved but reported | Feb 28, 2014 | Nov 24, 2015 | Resolved |
| cwa | Schedule Event achieved late but reported | Feb 28, 2014 | — | Open |
| cwa | Schedule Event reported late | Feb 28, 2014 | — | Open |
| cwa | Schedule Event reported late | Mar 31, 2012 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 31, 2012 | Oct 22, 2012 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 31, 2012 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2012 | Oct 22, 2012 | Resolved |
| cwa | Schedule Event reported late | Mar 31, 2010 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 31, 2010 | Oct 8, 2010 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 31, 2010 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2010 | Oct 8, 2010 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2009 | Aug 11, 2009 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 31, 2009 | Aug 11, 2009 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 31, 2009 | — | Open |
| cwa | Schedule Event reported late | Mar 31, 2009 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 28, 2008 | Aug 11, 2009 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 28, 2008 | — | Open |
| cwa | Schedule Event reported late | Mar 28, 2008 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 28, 2008 | Aug 11, 2009 | Resolved |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| Iron, total recoverable | DMR, Limited - Overdue | 68.80 mg/L | 1.00 | +6,780% | Jun 2021 | Resolved |
| Aluminum, total recoverable | DMR, Limited - Overdue | 26.70 mg/L | 0.75 | +3,460% | Jun 2021 | Resolved |
| Solids, total suspended | DMR, Limited - Overdue | 776.00 mg/L | 100.00 | +676% | Jun 2021 | Resolved |
| Lead, total recoverable | DMR, Limited - Overdue | 0.11 mg/L | 0.07 | +59% | Jun 2021 | Resolved |
| Iron, total recoverable | DMR, Limited - Overdue | 45.50 mg/L | 1.00 | +4,450% | Dec 2020 | Resolved |
| Solids, total suspended | DMR, Limited - Overdue | 1,030.00 mg/L | 100.00 | +930% | Dec 2020 | Resolved |
| Aluminum, total recoverable | DMR, Limited - Overdue | 24.60 mg/L | 0.75 | +3,180% | Dec 2020 | Resolved |
| Lead, total recoverable | DMR, Limited - Overdue | 0.08 mg/L | 0.07 | +16% | Dec 2020 | Resolved |
| Lead, total recoverable | DMR, Limited - Overdue | 0.07 mg/L | 0.07 | +3% | Jun 2020 | Resolved |
| Iron, total recoverable | DMR, Limited - Overdue | 5.84 mg/L | 1.00 | +484% | Jun 2020 | Resolved |
| Aluminum, total recoverable | DMR, Limited - Overdue | 4.62 mg/L | 0.75 | +516% | Jun 2020 | Resolved |
| Solids, total suspended | DMR, Limited - Overdue | 1,050.00 mg/L | 100.00 | +950% | Jun 2020 | Resolved |
| Solids, total suspended | DMR, Limited - Overdue | 767.00 mg/L | 100.00 | +667% | Dec 2019 | Resolved |
| Iron, total recoverable | DMR, Limited - Overdue | 92.00 mg/L | 1.00 | +9,100% | Dec 2019 | Resolved |
| Aluminum, total recoverable | DMR, Limited - Overdue | 57.20 mg/L | 0.75 | +7,527% | Dec 2019 | Resolved |
| Lead, total recoverable | DMR, Limited - Overdue | 0.09 mg/L | 0.07 | +35% | Dec 2019 | Resolved |
| Iron, total recoverable | DMR, Limited - Overdue | 11.40 mg/L | 1.00 | +1,040% | Dec 2015 | Resolved |
| Solids, total suspended | DMR, Limited - Overdue | 160.00 mg/L | 100.00 | +60% | Dec 2015 | Resolved |
| Aluminum, total recoverable | DMR, Limited - Overdue | 6.46 mg/L | 0.75 | +761% | Dec 2015 | Resolved |
Enforcement Actions
Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.