Non-Compliance
Clean Water Act
METALINE FALLS STP
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
SEWER POND RD
METALINE FALLS, WA 99153
View on map ↗ - County
- PEND OREILLE County
- Inspections
- 2 · last Mar 11, 2026
- Total Penalties
- $0
- Registry ID
- 110015531682
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
12
Water (CWA)
Qtrs Non-Compliant
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event unachieved and not reported | Oct 15, 2025 | Dec 23, 2025 | Resolved |
| cwa | Schedule Event achieved late but reported | Oct 15, 2025 | — | Open |
| cwa | Schedule Event unachieved but reported | Oct 15, 2025 | Dec 23, 2025 | Resolved |
| cwa | Schedule Event reported late | Oct 15, 2025 | — | Open |
| cwa | Schedule Event unachieved and not reported | May 15, 2025 | Jun 15, 2025 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 15, 2025 | — | Open |
| cwa | Schedule Event reported late | Mar 15, 2025 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 15, 2025 | May 12, 2025 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 15, 2025 | May 12, 2025 | Resolved |
| cwa | Schedule Event unachieved but reported | May 31, 2022 | Aug 15, 2022 | Resolved |
| cwa | Schedule Event reported late | May 31, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | May 31, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | May 31, 2022 | Aug 15, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | May 31, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | May 31, 2022 | Aug 15, 2022 | Resolved |
| cwa | Schedule Event reported late | May 31, 2022 | — | Open |
| cwa | Schedule Event unachieved but reported | May 31, 2022 | Aug 15, 2022 | Resolved |
| cwa | Schedule Event unachieved and not reported | May 15, 2022 | Aug 23, 2022 | Resolved |
| cwa | Schedule Event reported late | May 15, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | May 15, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | May 15, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | May 15, 2022 | Aug 23, 2022 | Resolved |
| cwa | Schedule Event unachieved but reported | May 15, 2022 | Aug 23, 2022 | Resolved |
| cwa | Schedule Event unachieved but reported | May 15, 2022 | Aug 23, 2022 | Resolved |
| cwa | Schedule Event reported late | May 15, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 15, 2021 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 15, 2021 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 15, 2021 | May 18, 2022 | Resolved |
| cwa | Schedule Event reported late | Mar 15, 2021 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 15, 2021 | May 18, 2022 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 15, 2021 | May 18, 2022 | Resolved |
| cwa | Schedule Event reported late | Mar 15, 2021 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 15, 2021 | May 18, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Dec 31, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Dec 31, 2020 | — | Open |
| cwa | Schedule Event unachieved and not reported | Dec 31, 2020 | Jan 31, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Oct 15, 2020 | Nov 15, 2020 | Resolved |
| cwa | Schedule Event unachieved and not reported | Oct 15, 2020 | Nov 15, 2020 | Resolved |
| cwa | Schedule Event reported late | Oct 15, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Oct 15, 2020 | — | Open |
| cwa | Schedule Event unachieved but reported | Oct 15, 2020 | Jan 11, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Oct 15, 2020 | Jan 11, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Oct 15, 2020 | Nov 15, 2020 | Resolved |
| cwa | Schedule Event unachieved but reported | Oct 15, 2020 | Jan 11, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Oct 15, 2020 | Jan 11, 2021 | Resolved |
| cwa | Schedule Event achieved late but reported | Oct 15, 2020 | — | Open |
| cwa | Schedule Event reported late | Oct 15, 2020 | — | Open |
| cwa | Schedule Event unachieved and not reported | May 15, 2020 | Jun 15, 2020 | Resolved |
| cwa | Schedule Event achieved late but reported | May 15, 2020 | — | Open |
| cwa | Schedule Event reported late | May 15, 2020 | — | Open |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| BOD, percent removal [total] | DMR, Limited - Numeric Violation | 81.50 % | 85.00 | +23% | Apr 2015 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 74.00 % | 85.00 | +73% | Mar 2015 | Open |
| BOD, percent removal [total] | DMR, Limited - Numeric Violation | 76.00 % | 85.00 | +60% | Mar 2015 | Open |
| Nitrogen, ammonia total [as N] | DMR, Limited - Numeric Violation | 20.60 mg/L | 12.10 | +70% | Feb 2015 | Open |
| Nitrogen, ammonia total [as N] | DMR, Limited - Numeric Violation | 14.70 mg/L | 7.00 | +110% | Feb 2015 | Open |
| Nitrogen, ammonia total [as N] | DMR, Limited - Numeric Violation | 8.48 mg/L | 7.00 | +21% | Jan 2015 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 74.20 % | 85.00 | +72% | Jan 2015 | Open |
| BOD, percent removal [total] | DMR, Limited - Numeric Violation | 83.60 % | 85.00 | +9% | Jan 2015 | Open |