REDONDO WWTP
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $85,200 in total penalties since records began.
- Address
-
515 S 288TH ST
DES MOINES, WA 98198
View on map ↗ - County
- KING County
- Inspections
- 2 · last Dec 31, 2024
- Total Penalties
- $85,200 · last Oct 2, 2023
- Registry ID
- 110061168454
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event unachieved and not reported | Mar 31, 2025 | May 1, 2025 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jul 8, 2024 | Jan 2, 2025 | Resolved |
| cwa | Schedule Event unachieved but reported | Jul 8, 2024 | Jan 2, 2025 | Resolved |
| cwa | Schedule Event achieved late but reported | Jul 8, 2024 | — | Open |
| cwa | Schedule Event reported late | Jul 8, 2024 | — | Open |
| cwa | Schedule Event reported late | Feb 6, 2024 | — | Open |
| cwa | Schedule Event unachieved but reported | Feb 6, 2024 | Mar 15, 2024 | Resolved |
| cwa | Schedule Event achieved late but reported | Feb 6, 2024 | — | Open |
| cwa | Schedule Event unachieved and not reported | Feb 6, 2024 | Mar 15, 2024 | Resolved |
| cwa | Schedule Event reported late | Jan 15, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 15, 2023 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jul 15, 2022 | Aug 15, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Jul 15, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jul 15, 2022 | Aug 15, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Jul 15, 2022 | — | Open |
| cwa | Schedule Event reported late | Jan 15, 2022 | — | Open |
| cwa | Schedule Event reported late | Jan 15, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jan 15, 2022 | Jul 7, 2022 | Resolved |
| cwa | Schedule Event unachieved but reported | Jan 15, 2022 | Jul 7, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 15, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 15, 2022 | — | Open |
| cwa | Schedule Event unachieved but reported | Jan 15, 2022 | Jul 7, 2022 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jan 15, 2022 | Jul 7, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Oct 15, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Oct 15, 2020 | — | Open |
| cwa | Schedule Event reported late | Oct 15, 2020 | — | Open |
| cwa | Schedule Event reported late | Oct 15, 2020 | — | Open |
| cwa | Schedule Event unachieved and not reported | Apr 15, 2020 | May 17, 2020 | Resolved |
| cwa | Schedule Event reported late | Apr 15, 2020 | — | Open |
| cwa | Schedule Event unachieved but reported | Apr 15, 2020 | May 17, 2020 | Resolved |
| cwa | Schedule Event achieved late but reported | Apr 15, 2020 | — | Open |
| cwa | Schedule Event reported late | Apr 15, 2020 | — | Open |
| cwa | Schedule Event unachieved and not reported | Apr 15, 2020 | May 17, 2020 | Resolved |
| cwa | Schedule Event achieved late but reported | Apr 15, 2020 | — | Open |
| cwa | Schedule Event unachieved but reported | Apr 15, 2020 | May 17, 2020 | Resolved |
| cwa | Schedule Event unachieved and not reported | Oct 15, 2019 | Nov 18, 2019 | Resolved |
| cwa | Schedule Event unachieved and not reported | Oct 15, 2019 | Nov 15, 2019 | Resolved |
| cwa | Schedule Event unachieved but reported | Oct 15, 2019 | Nov 18, 2019 | Resolved |
| cwa | Schedule Event reported late | Oct 15, 2019 | — | Open |
| cwa | Schedule Event achieved late but reported | Oct 15, 2019 | — | Open |
| cwa | Schedule Event unachieved and not reported | Oct 15, 2019 | Nov 18, 2019 | Resolved |
| cwa | Schedule Event reported late | Oct 15, 2019 | — | Open |
| cwa | Schedule Event achieved late but reported | Oct 15, 2019 | — | Open |
| cwa | Schedule Event unachieved but reported | Oct 15, 2019 | Nov 18, 2019 | Resolved |
| cwa | Schedule Event unachieved and not reported | Aug 30, 2019 | Sep 30, 2019 | Resolved |
| cwa | Schedule Event unachieved and not reported | Aug 30, 2019 | Sep 30, 2019 | Resolved |
| cwa | Schedule Event unachieved and not reported | Aug 30, 2019 | Sep 30, 2019 | Resolved |
| cwa | Schedule Event reported late | Apr 15, 2019 | — | Open |
| cwa | Schedule Event achieved late but reported | Apr 15, 2019 | — | Open |
| cwa | Schedule Event achieved late but reported | Apr 15, 2019 | — | Open |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| Coliform, fecal general | DMR, Limited - Numeric Violation | 406.00 MPN/100mL | 400.00 | +2% | May 2025 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 1,047.38 kg/d | 954.31 | +10% | Dec 2023 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 1,802.30 MPN/100mL | 400.00 | +351% | Aug 2023 | Open |
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 26.00 mg/L | 25.00 | +4% | Apr 2022 | Open |
| Carbonaceous oxygen demand, % removal | DMR, Limited - Numeric Violation | 82.90 % | 85.00 | +14% | Apr 2022 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 2,058.00 MPN/100mL | 400.00 | +415% | Apr 2022 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 490.50 MPN/100mL | 400.00 | +23% | Feb 2022 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 83.20 % | 85.00 | +12% | Jan 2022 | Open |
| Carbonaceous oxygen demand, % removal | DMR, Limited - Numeric Violation | 83.20 % | 85.00 | +12% | Jan 2022 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 84.00 % | 85.00 | +7% | Jan 2021 | Open |
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 50.00 mg/L | 40.00 | +25% | Jun 2020 | Open |
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 26.00 mg/L | 25.00 | +4% | May 2019 | Open |
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 42.40 mg/L | 40.00 | +6% | May 2019 | Open |
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 28.90 mg/L | 25.00 | +16% | Apr 2019 | Open |
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 49.60 mg/L | 40.00 | +24% | May 2018 | Open |
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 25.58 mg/L | 25.00 | +2% | May 2018 | Open |
| Carbonaceous oxygen demand, % removal | DMR, Limited - Numeric Violation | 83.80 % | 85.00 | +8% | Jan 2018 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 78.60 % | 85.00 | +43% | Feb 2017 | Open |
| Carbonaceous oxygen demand, % removal | DMR, Limited - Numeric Violation | 79.70 % | 85.00 | +35% | Feb 2017 | Open |
| Chlorine, total residual | DMR, Limited - Numeric Violation | 0.76 mg/L | 0.31 | +142% | Jan 2016 | Open |
| Carbonaceous oxygen demand, % removal | DMR, Limited - Numeric Violation | 79.20 % | 85.00 | +39% | Jan 2016 | Open |
| Chlorine, total residual | DMR, Limited - Numeric Violation | 0.17 mg/L | 0.12 | +40% | Dec 2015 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 3,547.00 MPN/100mL | 400.00 | +787% | Dec 2015 | Open |
| Carbonaceous oxygen demand, % removal | DMR, Limited - Numeric Violation | 78.80 % | 85.00 | +41% | Dec 2015 | Open |
| Chlorine, total residual | DMR, Limited - Numeric Violation | 1.50 mg/L | 0.31 | +381% | Dec 2015 | Open |
| Carbonaceous oxygen demand, % removal | DMR, Limited - Numeric Violation | 83.10 % | 85.00 | +13% | Nov 2015 | Open |
Enforcement Actions
Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.