ONTARIO (T) STP
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
2200 LAKE ROAD
ONTARIO, NY 14519
View on map ↗ - County
- WAYNE County
- Inspections
- 1 · last Dec 31, 2024
- Total Penalties
- $0 · last Aug 17, 2009
- Registry ID
- 110000760533
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event achieved late but reported | Mar 28, 2024 | — | Open |
| cwa | Schedule Event reported late | Mar 28, 2024 | — | Open |
| cwa | Schedule Event unachieved but reported | Feb 28, 2023 | — | Open |
| cwa | Schedule Event reported late | Feb 28, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Feb 28, 2023 | — | Open |
| cwa | Schedule Event unachieved but reported | Feb 28, 2023 | — | Open |
| cwa | Schedule Event reported late | Feb 28, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Feb 28, 2023 | — | Open |
| cwa | Schedule Event unachieved and not reported | Feb 28, 2023 | — | Open |
| cwa | Schedule Event unachieved and not reported | Feb 28, 2023 | — | Open |
| cwa | Schedule Event unachieved and not reported | Aug 28, 2020 | Aug 27, 2021 | Resolved |
| cwa | Schedule Event unachieved but reported | Aug 28, 2020 | Aug 27, 2021 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 28, 2020 | — | Open |
| cwa | Schedule Event reported late | Aug 28, 2020 | — | Open |
| cwa | Schedule Event reported late | Aug 28, 2019 | — | Open |
| cwa | Schedule Event unachieved and not reported | Aug 28, 2019 | Aug 27, 2021 | Resolved |
| cwa | Schedule Event unachieved but reported | Aug 28, 2019 | Aug 27, 2021 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 28, 2019 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 28, 2018 | — | Open |
| cwa | Schedule Event unachieved but reported | Aug 28, 2018 | Aug 27, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Aug 28, 2018 | Aug 27, 2021 | Resolved |
| cwa | Schedule Event reported late | Aug 28, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 28, 2014 | — | Open |
| cwa | Schedule Event reported late | Aug 28, 2014 | — | Open |
| cwa | Schedule Event reported late | Aug 28, 2013 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 28, 2013 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 28, 2012 | — | Open |
| cwa | Schedule Event unachieved and not reported | Aug 28, 2011 | Dec 22, 2011 | Resolved |
| cwa | Schedule Event unachieved but reported | Aug 28, 2011 | Dec 22, 2011 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 28, 2011 | — | Open |
| cwa | Schedule Event reported late | Aug 28, 2011 | — | Open |
| cwa | Schedule Event reported late | Aug 28, 2010 | — | Open |
| cwa | Schedule Event unachieved but reported | Aug 28, 2010 | Nov 4, 2010 | Resolved |
| cwa | Schedule Event unachieved and not reported | Aug 28, 2010 | Nov 4, 2010 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 28, 2010 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 28, 2009 | — | Open |
| cwa | Schedule Event unachieved and not reported | Aug 28, 2009 | Sep 28, 2009 | Resolved |
| cwa | Schedule Event reported late | Aug 28, 2009 | — | Open |
| cwa | Schedule Event unachieved but reported | Aug 28, 2009 | Sep 28, 2009 | Resolved |
| cwa | Schedule Event unachieved and not reported | Aug 28, 2008 | Oct 8, 2008 | Resolved |
| cwa | Schedule Event unachieved but reported | Aug 28, 2008 | Oct 8, 2008 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 28, 2008 | — | Open |
| cwa | Schedule Event reported late | Aug 28, 2008 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 28, 2007 | — | Open |
| cwa | Schedule Event reported late | Aug 28, 2007 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 28, 2006 | — | Open |
| cwa | Schedule Event unachieved and not reported | Aug 28, 2005 | Oct 1, 2005 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 28, 2005 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 28, 2004 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 28, 2003 | — | Open |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 45.40 kg/d | 45.40 | +99,999% | Nov 2025 | Open |
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 12.00 mg/L | 12.00 | +99,999% | Nov 2025 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 478.00 MPN/100mL | 400.00 | +20% | Aug 2025 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.20 MGD | 1.00 | +20% | Mar 2025 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.20 MGD | 1.00 | +20% | Mar 2025 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 1,247.00 MPN/100mL | 400.00 | +212% | May 2024 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 254.00 MPN/100mL | 200.00 | +27% | May 2024 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.13 MGD | 1.00 | +13% | Jan 2024 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.13 MGD | 1.00 | +13% | Jan 2024 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 460.00 MPN/100mL | 400.00 | +15% | Sep 2023 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 600.00 MPN/100mL | 400.00 | +50% | Aug 2023 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 358.00 MPN/100mL | 200.00 | +79% | Aug 2023 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 517.50 MPN/100mL | 200.00 | +159% | May 2023 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 600.00 MPN/100mL | 400.00 | +50% | May 2023 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.15 MGD | 1.00 | +15% | Mar 2023 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.15 MGD | 1.00 | +15% | Mar 2023 | Open |
| Nitrogen, ammonia total [as N] | DMR, Limited - Numeric Violation | 1.40 mg/L | 1.20 | +17% | May 2022 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.12 MGD | 1.00 | +12% | Feb 2022 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.12 MGD | 1.00 | +12% | Feb 2022 | Open |
| Nitrogen, ammonia total [as N] | DMR, Limited - Numeric Violation | 9.70 mg/L | 1.80 | +439% | Feb 2022 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.10 MGD | 1.00 | +10% | Feb 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.10 MGD | 1.00 | +10% | Feb 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.05 MGD | 1.00 | +5% | Nov 2018 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.05 MGD | 1.00 | +5% | Nov 2018 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 11.00 mg/L | 10.00 | +10% | Apr 2018 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 43.67 kg/d | 37.86 | +15% | Apr 2018 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.11 MGD | 1.00 | +11% | Jan 2018 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 11.00 mg/L | 10.00 | +10% | Jan 2018 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.11 MGD | 1.00 | +11% | Jan 2018 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 75.91 kg/d | 37.86 | +100% | Jan 2018 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.13 MGD | 1.00 | +13% | Nov 2017 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.13 MGD | 1.00 | +13% | Nov 2017 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.12 MGD | 1.00 | +12% | Apr 2017 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.12 MGD | 1.00 | +12% | Apr 2017 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.10 MGD | 1.00 | +10% | Feb 2016 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 1.10 MGD | 1.00 | +10% | Feb 2016 | Open |
Enforcement Actions
Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.