KINGSTON (C) WWTP
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
91-129 EAST STRAND STREET
KINGSTON, NY 12401
View on map ↗ - County
- ULSTER County
- Inspections
- 7 · last Nov 13, 2025
- Total Penalties
- $0 · last Feb 6, 2017
- Registry ID
- 110000735072
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Management Practice Violations - Improper Operation and Maintenance | Nov 13, 2025 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 31, 2023 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jan 31, 2022 | Mar 9, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 31, 2022 | — | Open |
| cwa | Schedule Event unachieved but reported | Jan 31, 2022 | Mar 9, 2022 | Resolved |
| cwa | Schedule Event reported late | Jan 31, 2022 | — | Open |
| cwa | Schedule Event reported late | Mar 16, 2021 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 16, 2021 | Jul 15, 2021 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 16, 2021 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 16, 2021 | Jul 15, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jan 31, 2020 | Jul 30, 2020 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 31, 2020 | — | Open |
| cwa | Schedule Event unachieved but reported | Jan 31, 2020 | Jul 30, 2020 | Resolved |
| cwa | Schedule Event reported late | Jan 31, 2020 | — | Open |
| cwa | Schedule Event unachieved and not reported | Dec 1, 2019 | Dec 1, 2020 | Resolved |
| cwa | Schedule Event unachieved but reported | Dec 1, 2019 | Dec 1, 2020 | Resolved |
| cwa | Schedule Event achieved late but reported | Dec 1, 2019 | — | Open |
| cwa | Schedule Event reported late | Dec 1, 2019 | — | Open |
| cwa | Schedule Event unachieved but reported | Dec 1, 2018 | Dec 1, 2020 | Resolved |
| cwa | Schedule Event unachieved and not reported | Dec 1, 2018 | Dec 1, 2020 | Resolved |
| cwa | Schedule Event reported late | Dec 1, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Dec 1, 2018 | — | Open |
| cwa | Schedule Event reported late | Jun 1, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jun 1, 2018 | — | Open |
| cwa | Schedule Event unachieved and not reported | Dec 1, 2017 | Jan 1, 2020 | Resolved |
| cwa | Schedule Event achieved late but reported | Dec 1, 2017 | — | Open |
| cwa | Schedule Event unachieved but reported | Dec 1, 2017 | Jan 1, 2020 | Resolved |
| cwa | Schedule Event reported late | Dec 1, 2017 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jun 1, 2017 | Jul 2, 2017 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 31, 2013 | — | Open |
| cwa | Schedule Event reported late | Jan 31, 2012 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 31, 2012 | — | Open |
| cwa | Schedule Event achieved late but reported | Apr 28, 2011 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jan 31, 2010 | May 3, 2010 | Resolved |
| cwa | Schedule Event unachieved but reported | Jan 31, 2010 | May 3, 2010 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 31, 2010 | — | Open |
| cwa | Schedule Event reported late | Jan 31, 2010 | — | Open |
| cwa | Schedule Event reported late | Jan 31, 2008 | — | Open |
| cwa | Schedule Event unachieved but reported | Jan 31, 2008 | May 1, 2008 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 31, 2008 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jan 31, 2008 | May 1, 2008 | Resolved |
| cwa | Schedule Event unachieved but reported | Aug 15, 2007 | Mar 31, 2008 | Resolved |
| cwa | Schedule Event unachieved and not reported | Aug 15, 2007 | Mar 31, 2008 | Resolved |
| cwa | Schedule Event reported late | Aug 15, 2007 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 15, 2007 | — | Open |
| cwa | Schedule Event achieved late but reported | Apr 28, 2007 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 28, 2007 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jan 31, 2007 | Mar 12, 2007 | Resolved |
| cwa | Schedule Event reported late | Jan 31, 2007 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 31, 2007 | — | Open |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| Coliform, fecal general | DMR, Limited - Numeric Violation | 399.00 MPN/100mL | 400.00 | +99,999% | Jul 2025 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 406.00 MPN/100mL | 200.00 | +99,999% | Jul 2025 | Open |
| Oxygen demand, ultimate | DMR, Limited - Numeric Violation | 2,235.95 kg/d | 2,224.60 | +1% | Aug 2023 | Open |
| Oxygen demand, ultimate | DMR, Limited - Numeric Violation | 2,283.62 kg/d | 2,224.60 | +3% | Jul 2023 | Open |
| Nitrogen, ammonia total [as N] | DMR, Limited - Numeric Violation | 19.40 mg/L | 18.00 | +8% | Jun 2023 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 94.00 MPN/100mL | 200.00 | +99,999% | Oct 2022 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | — MPN/100mL | 400.00 | +99,999% | Oct 2022 | Open |
| Oxygen demand, ultimate | DMR, Limited - Numeric Violation | 2,554.20 kg/d | 2,224.60 | +15% | Oct 2022 | Open |
| Nitrogen, ammonia total [as N] | DMR, Limited - Numeric Violation | 24.00 mg/L | 18.00 | +33% | Jun 2022 | Open |
| Oxygen demand, ultimate | DMR, Limited - Numeric Violation | 2,613.22 kg/d | 2,224.60 | +17% | Sep 2021 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 1.00 kg/d | 0.91 | +10% | Sep 2021 | Open |
| Oxygen demand, ultimate | DMR, Limited - Numeric Violation | 2,648.64 kg/d | 2,224.60 | +19% | Jul 2021 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 8.00 MPN/100mL | 400.00 | +99,999% | May 2021 | Open |
| Oxygen demand, ultimate | DMR, Limited - Numeric Violation | 2,289.52 kg/d | 2,224.60 | +3% | Jun 2019 | Open |
| Oxygen demand, ultimate | DMR, Limited - Numeric Violation | 2,973.25 kg/d | 2,224.60 | +34% | Oct 2018 | Open |
| Mercury, total [as Hg] | DMR, Limited - Numeric Violation | 0.00 mg/L | 0.00 | +300% | Feb 2017 | Open |
| Lead, total [as Pb] | DMR, Limited - Numeric Violation | 0.32 kg/d | 0.20 | +56% | Sep 2015 | Open |
Enforcement Actions
Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.