LOWRY CITY PWS
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
SOUTH TAYLOR
LOWRY CITY, MO 64763
View on map ↗ - County
- ST. CLAIR County
- Inspections
- 1 · last Dec 1, 2025
- Total Penalties
- $0
- Registry ID
- 110039790474
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event unachieved and not reported | Jan 28, 2026 | Feb 28, 2026 | Resolved |
| cwa | Schedule Event unachieved but reported | Jan 28, 2025 | Jul 3, 2025 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 28, 2025 | — | Open |
| cwa | Schedule Event reported late | Jan 28, 2025 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jan 28, 2025 | Jul 3, 2025 | Resolved |
| cwa | Reporting Violations - Failure to Submit DMRs | Dec 26, 2024 | — | Open |
| cwa | Reporting Violations - Improper/ Incorrect Reporting | Aug 2, 2024 | — | Open |
| cwa | Reporting Violations - Improper/ Incorrect Reporting | Jun 21, 2024 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 1, 2024 | Jul 26, 2024 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 1, 2024 | — | Open |
| cwa | Schedule Event reported late | Mar 1, 2024 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 1, 2024 | Jul 26, 2024 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 1, 2021 | — | Open |
| cwa | Schedule Event unachieved but reported | Jan 28, 2021 | Jan 27, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 28, 2021 | — | Open |
| cwa | Schedule Event reported late | Jan 28, 2021 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jan 28, 2021 | Jan 27, 2022 | Resolved |
| cwa | Schedule Event reported late | Aug 1, 2020 | — | Open |
| cwa | Schedule Event unachieved and not reported | Aug 1, 2020 | Jan 4, 2021 | Resolved |
| cwa | Schedule Event unachieved but reported | Aug 1, 2020 | Jan 4, 2021 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 1, 2020 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jan 28, 2020 | Nov 25, 2020 | Resolved |
| cwa | Schedule Event reported late | Jan 28, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 28, 2020 | — | Open |
| cwa | Schedule Event unachieved but reported | Jan 28, 2020 | Nov 25, 2020 | Resolved |
| cwa | Schedule Event unachieved but reported | Aug 1, 2019 | Jan 4, 2021 | Resolved |
| cwa | Schedule Event reported late | Aug 1, 2019 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 1, 2019 | — | Open |
| cwa | Schedule Event unachieved and not reported | Aug 1, 2019 | Jan 4, 2021 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 1, 2018 | — | Open |
| cwa | Schedule Event unachieved and not reported | Aug 1, 2018 | Dec 10, 2018 | Resolved |
| cwa | Schedule Event reported late | Aug 1, 2018 | — | Open |
| cwa | Schedule Event unachieved but reported | Aug 1, 2018 | Dec 10, 2018 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 28, 2018 | — | Open |
| cwa | Schedule Event unachieved and not reported | Feb 1, 2017 | Jun 29, 2017 | Resolved |
| cwa | Schedule Event unachieved but reported | Feb 1, 2017 | Jun 29, 2017 | Resolved |
| cwa | Schedule Event achieved late but reported | Feb 1, 2017 | — | Open |
| cwa | Schedule Event reported late | Feb 1, 2017 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 1, 2016 | — | Open |
| cwa | Schedule Event achieved late but reported | Oct 30, 2013 | — | Open |
| cwa | Schedule Event reported late | Oct 30, 2012 | — | Open |
| cwa | Schedule Event unachieved but reported | Oct 30, 2012 | — | Open |
| cwa | Schedule Event unachieved and not reported | Oct 30, 2012 | — | Open |
| cwa | Schedule Event achieved late but reported | Oct 30, 2012 | — | Open |
| cwa | Schedule Event reported late | Oct 30, 2011 | — | Open |
| cwa | Schedule Event unachieved and not reported | Oct 30, 2011 | Jan 22, 2012 | Resolved |
| cwa | Schedule Event unachieved but reported | Oct 30, 2011 | Jan 22, 2012 | Resolved |
| cwa | Schedule Event achieved late but reported | Oct 30, 2011 | — | Open |
| cwa | Schedule Event achieved late but reported | May 16, 2010 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 17, 2010 | — | Open |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| E. coli | DMR, Limited - Numeric Violation | 291.00 MPN/100mL | 206.00 | +41% | May 2025 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 90.00 mg/L | 80.00 | +13% | May 2025 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 53.00 % | 65.00 | +34% | May 2025 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 60.00 % | 65.00 | +14% | Feb 2024 | Open |
| Oil and grease [soxhlet extr.] tot. | DMR, Limited - Numeric Violation | 37.00 mg/L | 10.00 | +270% | Jun 2022 | Open |
| Oil and grease [soxhlet extr.] tot. | DMR, Limited - Numeric Violation | 37.00 mg/L | 15.00 | +147% | Jun 2022 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 60.00 mg/L | 45.00 | +33% | Apr 2020 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 36.00 % | 65.00 | +83% | Mar 2020 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 63.00 mg/L | 45.00 | +40% | Mar 2020 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 4.00 % | 65.00 | +174% | Mar 2020 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 55.00 mg/L | 45.00 | +22% | May 2019 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 84.00 mg/L | 80.00 | +5% | Feb 2016 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 46.00 mg/L | 45.00 | +2% | Apr 2015 | Open |
Enforcement Actions
Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.