EmissionsLookup
Non-Compliance Clean Water Act

JASPER WWTF

Quick Summary

  • Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
  • Assessed $0 in total penalties since records began.
Address
121 EAST GRAND
JASPER, MO 64755
View on map ↗
County
JASPER County
Inspections
1 · last Apr 26, 2023
Total Penalties
$0
Registry ID
110009877623

Compliance Status (Last 12 Quarters)

Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.

12
Water (CWA)
Qtrs Non-Compliant

Compliance Violations

Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.

Program Type Violation Date Return to Compliance Status
cwa Effluent Violations - Numeric effluent violation Sep 17, 2025 Open
cwa Schedule Event unachieved and not reported Jan 28, 2022 Feb 28, 2022 Resolved
cwa Schedule Event unachieved but reported Jan 28, 2021 Mar 5, 2021 Resolved
cwa Schedule Event unachieved and not reported Jan 28, 2021 Mar 5, 2021 Resolved
cwa Schedule Event reported late Jan 28, 2021 Open
cwa Schedule Event reported late Jan 28, 2021 Open
cwa Schedule Event achieved late but reported Jan 28, 2021 Open
cwa Schedule Event achieved late but reported Jan 28, 2021 Open
cwa Schedule Event unachieved but reported Jan 28, 2021 Mar 5, 2021 Resolved
cwa Schedule Event unachieved and not reported Jan 28, 2021 Mar 5, 2021 Resolved
cwa Schedule Event reported late Jul 28, 2020 Open
cwa Schedule Event achieved late but reported Jul 28, 2020 Open
cwa Schedule Event unachieved but reported Jul 28, 2020 Jul 16, 2021 Resolved
cwa Schedule Event unachieved and not reported Jul 28, 2020 Jul 16, 2021 Resolved
cwa Schedule Event achieved late but reported Jan 28, 2020 Open
cwa Schedule Event achieved late but reported Jan 28, 2020 Open
cwa Schedule Event achieved late but reported Jul 28, 2019 Open
cwa Schedule Event unachieved but reported Jul 28, 2019 Oct 4, 2019 Resolved
cwa Schedule Event unachieved and not reported Jul 28, 2019 Oct 4, 2019 Resolved
cwa Schedule Event reported late Jul 28, 2019 Open
cwa Schedule Event achieved late but reported Jan 28, 2019 Open
cwa Schedule Event achieved late but reported Jan 28, 2019 Open
cwa Schedule Event achieved late but reported Jul 1, 2018 Open
cwa Schedule Event achieved late but reported Jul 1, 2018 Open
cwa Schedule Event achieved late but reported Mar 1, 2018 Open
cwa Schedule Event achieved late but reported Mar 1, 2018 Open
cwa Schedule Event achieved late but reported Feb 1, 2018 Open
cwa Schedule Event achieved late but reported Jan 28, 2017 Open
cwa Schedule Event achieved late but reported Jan 28, 2016 Open
cwa Schedule Event achieved late but reported Jan 28, 2016 Open
cwa Schedule Event achieved late but reported Jan 28, 2015 Open
cwa Schedule Event unachieved but reported Jul 1, 2014 Jan 2, 2015 Resolved
cwa Schedule Event unachieved and not reported Jul 1, 2014 Jan 2, 2015 Resolved
cwa Schedule Event achieved late but reported Jul 1, 2014 Open
cwa Schedule Event reported late Jul 1, 2014 Open
cwa Schedule Event achieved late but reported Jan 28, 2014 Open
cwa Schedule Event achieved late but reported Jan 1, 2014 Open
cwa Schedule Event achieved late but reported Apr 30, 2013 Open
cwa Schedule Event reported late Apr 30, 2013 Open
cwa Schedule Event unachieved and not reported Apr 30, 2013 May 31, 2013 Resolved
cwa Schedule Event unachieved but reported Apr 30, 2013 May 31, 2013 Resolved
cwa Schedule Event achieved late but reported Jan 28, 2013 Open
cwa Schedule Event reported late Aug 31, 2012 Open
cwa Schedule Event achieved late but reported Aug 31, 2012 Open
cwa Schedule Event unachieved but reported Aug 31, 2012 Open
cwa Schedule Event unachieved and not reported Aug 31, 2012 Open
cwa Schedule Event reported late Apr 30, 2012 Open
cwa Schedule Event achieved late but reported Apr 30, 2012 Open
cwa Schedule Event achieved late but reported Jan 28, 2012 Open
cwa Schedule Event reported late Oct 31, 2010 Open

Discharge Limit Exceedances

Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.

Pollutant Violation Reported Limit Exceedance Period Status
Solids, total suspended DMR, Limited - Numeric Violation 30.80 mg/L 30.00 +3% Feb 2026 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 30.30 mg/L 10.10 +200% Feb 2026 Open
BOD, 5-day, 20 deg. C DMR, Limited - Numeric Violation 32.30 mg/L 30.00 +8% Feb 2026 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 30.30 mg/L 2.70 +1,022% Feb 2026 Open
BOD, 5-day, percent removal DMR, Limited - Numeric Violation 84.40 % 85.00 +4% Feb 2026 Open
Solids, suspended percent removal DMR, Limited - Numeric Violation 49.90 % 85.00 +234% Feb 2026 Open
Solids, suspended percent removal DMR, Limited - Numeric Violation 70.00 % 85.00 +100% Jan 2026 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 21.40 mg/L 3.10 +590% Jan 2026 Open
BOD, 5-day, 20 deg. C DMR, Limited - Numeric Violation 39.60 mg/L 30.00 +32% Jan 2026 Open
BOD, 5-day, percent removal DMR, Limited - Numeric Violation 70.00 % 85.00 +100% Jan 2026 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 21.40 mg/L 12.10 +77% Jan 2026 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 8.90 mg/L 3.10 +187% Dec 2025 Resolved
BOD, 5-day, percent removal DMR, Limited - Numeric Violation 79.00 % 85.00 +40% Dec 2025 Open
BOD, 5-day, 20 deg. C DMR, Limited - Numeric Violation 56.80 mg/L 30.00 +89% Dec 2025 Open
BOD, 5-day, 20 deg. C DMR, Limited - Numeric Violation 56.80 mg/L 45.00 +26% Dec 2025 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 19.90 mg/L 12.10 +64% Nov 2025 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 19.90 mg/L 3.10 +542% Nov 2025 Resolved
BOD, 5-day, percent removal DMR, Limited - Numeric Violation 82.00 % 85.00 +20% Nov 2025 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 26.40 mg/L 12.10 +118% Oct 2025 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 26.40 mg/L 2.50 +956% Oct 2025 Resolved
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 25.00 mg/L 12.10 +107% Sep 2025 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 25.00 mg/L 1.80 +1,289% Sep 2025 Resolved
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 10.20 mg/L 10.10 +1% Aug 2025 Open
Solids, suspended percent removal DMR, Limited - Numeric Violation 59.00 % 85.00 +173% Aug 2025 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 10.20 mg/L 1.30 +685% Aug 2025 Resolved
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 9.10 mg/L 1.50 +507% Jul 2025 Resolved
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 4.80 mg/L 1.70 +182% Jun 2025 Resolved
Solids, suspended percent removal DMR, Limited - Numeric Violation 73.00 % 85.00 +80% Jun 2025 Open
Solids, suspended percent removal DMR, Limited - Numeric Violation 69.00 % 85.00 +107% May 2025 Open
BOD, 5-day, percent removal DMR, Limited - Numeric Violation 68.00 % 85.00 +113% May 2025 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 8.70 mg/L 2.20 +295% May 2025 Resolved
BOD, 5-day, percent removal DMR, Limited - Numeric Violation 81.00 % 85.00 +27% Apr 2025 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 13.30 mg/L 12.10 +10% Apr 2025 Open
Solids, suspended percent removal DMR, Limited - Numeric Violation 81.00 % 85.00 +27% Apr 2025 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 13.30 mg/L 2.70 +393% Apr 2025 Resolved
Solids, suspended percent removal DMR, Limited - Numeric Violation 47.00 % 85.00 +253% Mar 2025 Open
Solids, total suspended DMR, Limited - Numeric Violation 38.00 mg/L 30.00 +27% Mar 2025 Open
Solids, suspended percent removal DMR, Limited - Numeric Violation 0.00 % 85.00 +567% Feb 2025 Open
BOD, 5-day, percent removal DMR, Limited - Numeric Violation 0.00 % 85.00 +567% Feb 2025 Open
Solids, suspended percent removal DMR, Limited - Numeric Violation 0.00 % 85.00 +567% Jan 2025 Open
BOD, 5-day, percent removal DMR, Limited - Numeric Violation 0.00 % 85.00 +567% Jan 2025 Open
Solids, suspended percent removal DMR, Limited - Numeric Violation 0.00 % 85.00 +567% Dec 2024 Open
BOD, 5-day, percent removal DMR, Limited - Numeric Violation 0.00 % 85.00 +567% Dec 2024 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 2.90 mg/L 1.80 +61% Sep 2024 Resolved
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 3.00 mg/L 1.30 +131% Aug 2024 Resolved
Solids, suspended percent removal DMR, Limited - Numeric Violation 44.00 % 85.00 +273% Jul 2024 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 3.10 mg/L 1.50 +107% Jul 2024 Resolved
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 3.60 mg/L 1.70 +112% Jun 2024 Resolved
Solids, suspended percent removal DMR, Limited - Numeric Violation 77.00 % 85.00 +53% Jun 2024 Open
BOD, 5-day, percent removal DMR, Limited - Numeric Violation 77.80 % 85.00 +48% May 2024 Open

Enforcement Actions

Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.

State Administrative Order of Consent
Clean Water Act · Case MO-NBF000003161 · Sep 29, 2022
Civil Judicial Action
Clean Water Act · Case MO-N00000252 · Oct 28, 1993

Other facilities in JASPER County, MO

FEDEX EXPRESS JLNA
JOPLIN, MO
AESIR/ZAF TECHNOLOGIES
JOPLIN, MO · Administrative and Support and Waste Management
MAWC, PURCELL WWTF
PURCELL, MO
All facilities in MO →