EmissionsLookup
Non-Compliance Clean Water Act

HOLLY GROVE, CITY OF

Quick Summary

  • Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
  • Assessed $0 in total penalties since records began.
Address
GABLE END ROAD
HOLLY GROVE, AR 72069
View on map ↗
County
MONROE County
Industry
Utilities
NAICS (North American Industry Classification)
221320
Total Penalties
$0 · last Sep 10, 2003
Registry ID
110010066917

Compliance Status (Last 12 Quarters)

Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.

3
Water (CWA)
Qtrs Non-Compliant

Compliance Violations

Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.

Program Type Violation Date Return to Compliance Status
cwa Schedule Event achieved late but reported Aug 2, 2003 Open
cwa Schedule Event unachieved and not reported Aug 2, 2003 Sep 24, 2009 Resolved
cwa Reporting Violations - Late Submittal of DMRs Apr 30, 2003 Open
cwa Reporting Violations - Late Submittal of DMRs Mar 31, 2003 Open
cwa Reporting Violations - Late Submittal of DMRs Jan 31, 2003 Open
cwa Reporting Violations - Late Submittal of DMRs Sep 30, 2002 Open
cwa Reporting Violations - Late Submittal of DMRs May 31, 2002 Open
cwa Permit Violations - Violation Specified in Comment Feb 15, 1994 Open
cwa Schedule Event achieved late but reported Dec 1, 1992 Open
cwa Schedule Event unachieved and not reported Dec 1, 1992 Jun 2, 1994 Resolved
cwa Schedule Event achieved late but reported Nov 15, 1991 Open
cwa Schedule Event unachieved and not reported Nov 15, 1991 Jun 2, 1994 Resolved
cwa Schedule Event achieved late but reported Aug 15, 1991 Open
cwa Permit Violations - Violation Specified in Comment May 11, 1989 Open
cwa Effluent Violations - Unapproved Bypass Jan 19, 1988 Open
cwa Permit Violations - Violation Specified in Comment Jan 19, 1988 Open

Discharge Limit Exceedances

Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.

Pollutant Violation Reported Limit Exceedance Period Status
Oxygen, dissolved [DO] DMR, Limited - Numeric Violation 1.38 mg/L 2.00 +31% Apr 2024 Open

Enforcement Actions

Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.

State Administrative Order of Consent
Clean Water Act · Case AR-N00007483 · Sep 10, 2003
$500
State CWA Non Penalty AO
Clean Water Act · Case AR-N00001905 · May 31, 1991