HOLLEY (V) STP
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
FRISBEE TERRACE
HOLLEY, NY 14470
View on map ↗ - County
- ORLEANS County
- Inspections
- 4 · last Jun 28, 2023
- Total Penalties
- $0 · last Feb 1, 2005
- Registry ID
- 110006621129
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event reported late | Apr 30, 2024 | — | Open |
| cwa | Schedule Event achieved late but reported | Apr 30, 2024 | — | Open |
| cwa | Schedule Event unachieved but reported | Apr 30, 2024 | — | Open |
| cwa | Schedule Event unachieved and not reported | Apr 30, 2024 | — | Open |
| cwa | Schedule Event reported late | Sep 29, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Sep 29, 2023 | — | Open |
| cwa | Schedule Event unachieved but reported | Sep 29, 2023 | Jan 31, 2024 | Resolved |
| cwa | Schedule Event unachieved and not reported | Sep 29, 2023 | Jan 31, 2024 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 28, 2021 | Jan 4, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 28, 2021 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 28, 2021 | Jan 4, 2022 | Resolved |
| cwa | Schedule Event reported late | Mar 28, 2021 | — | Open |
| cwa | Schedule Event reported late | Mar 28, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 28, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 1, 2019 | — | Open |
| cwa | Schedule Event reported late | Mar 1, 2019 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 1, 2018 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 1, 2018 | May 10, 2018 | Resolved |
| cwa | Schedule Event reported late | Mar 1, 2018 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 1, 2018 | May 10, 2018 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 28, 2017 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 1, 2017 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 1, 2017 | Jun 16, 2017 | Resolved |
| cwa | Schedule Event reported late | Mar 1, 2017 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 1, 2017 | Jun 16, 2017 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 28, 2016 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 1, 2016 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 28, 2015 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 1, 2014 | Mar 1, 2015 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 1, 2014 | Mar 1, 2015 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 1, 2014 | — | Open |
| cwa | Schedule Event reported late | Mar 1, 2014 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jun 28, 2007 | Jun 1, 2008 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jun 28, 2007 | Jun 1, 2008 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 28, 2007 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 31, 2007 | — | Open |
| cwa | Schedule Event reported late | Jan 31, 2007 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jun 28, 2006 | Jun 1, 2008 | Resolved |
| cwa | Schedule Event unachieved and not reported | Nov 1, 2005 | Jun 1, 2008 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jun 28, 2005 | Jun 1, 2008 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jun 1, 2005 | Jun 1, 2008 | Resolved |
| cwa | Schedule Event achieved late but reported | Jun 1, 2005 | — | Open |
| cwa | Schedule Event achieved late but reported | Jun 28, 1998 | — | Open |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.51 MGD | 0.45 | +13% | Apr 2024 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.54 MGD | 0.45 | +20% | Mar 2023 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.51 MGD | 0.45 | +13% | Feb 2022 | Open |
| Solids, total dissolved | DMR, Limited - Numeric Violation | 1,200.00 mg/L | 1,100.00 | +9% | Dec 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.48 MGD | 0.45 | +7% | Dec 2019 | Open |
| Solids, total dissolved | DMR, Limited - Numeric Violation | 1,200.00 mg/L | 1,100.00 | +9% | Feb 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.48 MGD | 0.45 | +7% | Feb 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.52 MGD | 0.45 | +16% | Apr 2018 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.50 MGD | 0.45 | +11% | Mar 2018 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.46 MGD | 0.45 | +2% | Jan 2018 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.46 MGD | 0.45 | +2% | Nov 2017 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.57 MGD | 0.45 | +27% | May 2017 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 82.00 % | 85.00 | +20% | May 2017 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 71.28 kg/d | 51.30 | +39% | Apr 2017 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 130.30 kg/d | 77.18 | +69% | Apr 2017 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.78 MGD | 0.45 | +73% | Apr 2017 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 63.00 % | 85.00 | +147% | Apr 2017 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 54.48 kg/d | 51.30 | +6% | Apr 2017 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 40.00 % | 85.00 | +300% | Apr 2017 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 83.99 kg/d | 77.18 | +9% | Apr 2017 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.48 MGD | 0.45 | +7% | Mar 2017 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.47 MGD | 0.45 | +4% | Jan 2017 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.47 MGD | 0.45 | +4% | Mar 2016 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.49 MGD | 0.45 | +9% | Feb 2016 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.53 MGD | 0.45 | +18% | Apr 2015 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.53 MGD | 0.45 | +18% | Mar 2015 | Open |