EmissionsLookup
Non-Compliance Clean Water Act

LASALLE EAST SIDE WWTP, CITY OF

Quick Summary

  • Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
  • Assessed $0 in total penalties since records began.
Address
TOWNSHIP 33N, RANGE 1E SECTION 11
LA SALLE, IL 61301
View on map ↗
County
LASALLE County
Total Penalties
$0
Registry ID
110044898135

Compliance Status (Last 12 Quarters)

Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.

10
Water (CWA)
Qtrs Non-Compliant

Compliance Violations

Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.

Program Type Violation Date Return to Compliance Status
cwa Schedule Event reported late Jan 31, 2026 Open
cwa Schedule Event unachieved and not reported Jan 31, 2026 Mar 12, 2026 Resolved
cwa Schedule Event achieved late but reported Jan 31, 2026 Open
cwa Schedule Event unachieved but reported Jan 31, 2026 Mar 12, 2026 Resolved
cwa Schedule Event achieved late but reported Nov 30, 2025 Open
cwa Schedule Event reported late Nov 30, 2025 Open
cwa Schedule Event unachieved and not reported Nov 30, 2025 Mar 13, 2026 Resolved
cwa Schedule Event unachieved but reported Nov 30, 2025 Mar 13, 2026 Resolved
cwa Schedule Event achieved late but reported Oct 31, 2025 Open
cwa Schedule Event reported late Oct 31, 2025 Open
cwa Schedule Event unachieved but reported Oct 31, 2025 Dec 1, 2025 Resolved
cwa Schedule Event unachieved and not reported Oct 31, 2025 Dec 1, 2025 Resolved
cwa Schedule Event achieved late but reported Jul 31, 2025 Open
cwa Schedule Event unachieved and not reported Jul 31, 2025 Sep 24, 2025 Resolved
cwa Schedule Event unachieved but reported Jul 31, 2025 Sep 24, 2025 Resolved
cwa Schedule Event reported late Jul 31, 2025 Open
cwa Schedule Event unachieved but reported May 31, 2025 Mar 13, 2026 Resolved
cwa Schedule Event unachieved and not reported May 31, 2025 Mar 13, 2026 Resolved
cwa Schedule Event reported late May 31, 2025 Open
cwa Schedule Event achieved late but reported May 31, 2025 Open
cwa Schedule Event reported late Nov 30, 2024 Open
cwa Schedule Event unachieved but reported Nov 30, 2024 Mar 13, 2026 Resolved
cwa Schedule Event unachieved and not reported Nov 30, 2024 Mar 13, 2026 Resolved
cwa Schedule Event achieved late but reported Nov 30, 2024 Open
cwa Schedule Event unachieved but reported May 31, 2024 Mar 13, 2026 Resolved
cwa Schedule Event achieved late but reported May 31, 2024 Open
cwa Schedule Event reported late May 31, 2024 Open
cwa Schedule Event unachieved and not reported May 31, 2024 Mar 13, 2026 Resolved
cwa Schedule Event achieved late but reported Nov 30, 2023 Open
cwa Schedule Event reported late Jul 31, 2023 Open
cwa Schedule Event unachieved and not reported Jul 31, 2023 Nov 13, 2023 Resolved
cwa Schedule Event achieved late but reported Jul 31, 2023 Open
cwa Schedule Event unachieved but reported Jul 31, 2023 Nov 13, 2023 Resolved
cwa Schedule Event achieved late but reported May 31, 2023 Open
cwa Schedule Event reported late May 31, 2023 Open
cwa Schedule Event unachieved and not reported May 31, 2023 Dec 1, 2023 Resolved
cwa Schedule Event unachieved but reported May 31, 2023 Dec 1, 2023 Resolved
cwa Schedule Event unachieved and not reported Nov 30, 2022 Dec 1, 2023 Resolved
cwa Schedule Event unachieved but reported Nov 30, 2022 Dec 1, 2023 Resolved
cwa Schedule Event achieved late but reported Nov 30, 2022 Open
cwa Schedule Event reported late Nov 30, 2022 Open
cwa Schedule Event unachieved and not reported May 31, 2022 Dec 1, 2023 Resolved
cwa Schedule Event reported late May 31, 2022 Open
cwa Schedule Event achieved late but reported May 31, 2022 Open
cwa Schedule Event unachieved but reported May 31, 2022 Dec 1, 2023 Resolved
cwa Schedule Event achieved late but reported Jan 31, 2022 Open
cwa Schedule Event achieved late but reported Apr 28, 2021 Open
cwa Schedule Event achieved late but reported Jan 31, 2020 Open
cwa Schedule Event unachieved but reported Jan 31, 2020 Jul 20, 2020 Resolved
cwa Schedule Event reported late Jan 31, 2020 Open

Discharge Limit Exceedances

Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.

Pollutant Violation Reported Limit Exceedance Period Status
Phosphorus, total [as P] DMR, Limited - Numeric Violation 1.06 mg/L 1.00 +6% May 2022 Open
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.60 mg/L 0.50 +20% Apr 2021 Resolved
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 7.00 mg/L 2.80 +150% Mar 2021 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 47.76 kg/d 20.43 +134% Feb 2021 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 92.00 mg/L 3.60 +2,456% Feb 2021 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 16.53 kg/d 11.80 +40% Feb 2021 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 27.85 mg/L 2.10 +1,226% Feb 2021 Open
Solids, total suspended DMR, Limited - Numeric Violation 25.30 mg/L 24.00 +5% Jan 2021 Open
Solids, total suspended DMR, Limited - Numeric Violation 16.40 mg/L 12.00 +37% Jan 2021 Open
Phosphorus, total [as P] DMR, Limited - Numeric Violation 1.10 mg/L 0.50 +120% Jan 2021 Resolved
Solids, total suspended DMR, Limited - Numeric Violation 14.30 mg/L 12.00 +19% Dec 2020 Open
Phosphorus, total [as P] DMR, Limited - Numeric Violation 1.00 mg/L 0.50 +100% Dec 2020 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.90 mg/L 0.50 +80% Nov 2020 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.90 mg/L 0.50 +80% Oct 2020 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.70 mg/L 0.50 +40% Aug 2020 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.60 mg/L 0.50 +20% Mar 2020 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.70 mg/L 0.50 +40% Feb 2020 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.70 mg/L 0.50 +40% Jan 2020 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.80 mg/L 0.50 +60% Dec 2019 Resolved
Solids, total suspended DMR, Limited - Numeric Violation 13.40 mg/L 12.00 +12% Dec 2019 Open
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.80 mg/L 0.50 +60% Sep 2019 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.70 mg/L 0.50 +40% Aug 2019 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.60 mg/L 0.50 +20% Aug 2018 Open
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.60 mg/L 0.50 +20% Jan 2018 Open
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.70 mg/L 0.50 +40% Dec 2017 Open
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.60 mg/L 0.50 +20% Oct 2017 Open
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.60 mg/L 0.50 +20% Jun 2017 Open
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.60 mg/L 0.50 +20% Sep 2016 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.80 mg/L 0.50 +60% Jun 2016 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 0.70 mg/L 0.50 +40% May 2016 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 2.10 mg/L 0.50 +320% Jul 2015 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 2.80 mg/L 0.50 +460% Jun 2015 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 3.70 mg/L 0.50 +640% May 2015 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 4.00 mg/L 0.50 +700% Apr 2015 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 2.20 mg/L 0.50 +340% Mar 2015 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 1.00 mg/L 0.50 +100% Feb 2015 Resolved
Phosphorus, total [as P] DMR, Limited - Numeric Violation 1.60 mg/L 0.50 +220% Jan 2015 Resolved

Other facilities in LASALLE County, IL

MANLEY BROTHERS OF INDIANA
TROY GROVE, IL · Mining, Quarrying, and Oil and Gas Extraction
All facilities in IL →