Non-Compliance
Clean Water Act
MOBLEY/FISHER PIT
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
7105 LAUREL AIRPORT RD
BILLINGS, MT 59106
View on map ↗ - County
- YELLOWSTONE County
- Inspections
- 2 · last May 9, 2024
- Total Penalties
- $0
- Registry ID
- 110014326372
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
1
Water (CWA)
Qtrs Non-Compliant
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event unachieved but reported | Feb 15, 2022 | Jan 19, 2023 | Resolved |
| cwa | Schedule Event unachieved and not reported | Feb 15, 2022 | Jan 19, 2023 | Resolved |
| cwa | Schedule Event achieved late but reported | Feb 15, 2022 | — | Open |
| cwa | Schedule Event reported late | Feb 15, 2022 | — | Open |
| cwa | Schedule Event unachieved but reported | Feb 15, 2021 | Mar 13, 2023 | Resolved |
| cwa | Schedule Event unachieved and not reported | Feb 15, 2021 | Mar 13, 2023 | Resolved |
| cwa | Schedule Event achieved late but reported | Feb 15, 2021 | — | Open |
| cwa | Schedule Event reported late | Feb 15, 2021 | — | Open |
| cwa | Schedule Event unachieved but reported | Feb 15, 2020 | Mar 13, 2023 | Resolved |
| cwa | Schedule Event unachieved and not reported | Feb 15, 2020 | Mar 13, 2023 | Resolved |
| cwa | Schedule Event reported late | Feb 15, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Feb 15, 2020 | — | Open |
| cwa | Schedule Event unachieved and not reported | Feb 15, 2019 | Mar 13, 2023 | Resolved |
| cwa | Schedule Event unachieved but reported | Feb 15, 2019 | Mar 13, 2023 | Resolved |
| cwa | Schedule Event reported late | Feb 15, 2019 | — | Open |
| cwa | Schedule Event achieved late but reported | Feb 15, 2019 | — | Open |
| cwa | Monitoring Violations - Frequency of Sampling Violation | Oct 12, 2016 | Dec 5, 2016 | Resolved |
| cwa | Management Practice Violations - Failure to Maintain Records | Oct 12, 2016 | Dec 5, 2016 | Resolved |
| cwa | Monitoring Violations - Analysis not Conducted | Oct 12, 2016 | Dec 5, 2016 | Resolved |
| cwa | Reporting Violations - Failure to Submit DMRs | May 20, 2015 | Dec 20, 2018 | Resolved |
| cwa | WW Storm Water Construction - Failure to Maintain Records | May 20, 2015 | Dec 20, 2018 | Resolved |
| cwa | WW Storm Water Construction - Failure to Implement SWPPP/SWMP | May 20, 2015 | Oct 15, 2015 | Resolved |
| cwa | WW Storm Water Construction - Failure to develop any or adequate SWPPP/SWMP | May 20, 2015 | Oct 15, 2015 | Resolved |
| cwa | WW Storm Water Construction - Failure to Conduct Inspections | May 20, 2015 | Dec 20, 2018 | Resolved |
| cwa | WW Storm Water Construction - Discharge without a permit | May 20, 2015 | Dec 20, 2018 | Resolved |
| cwa | WW Storm Water Construction - Failure to properly install/implement BMPs | May 20, 2015 | Dec 20, 2018 | Resolved |
| cwa | WW Storm Water Construction - Failure to properly operate and maintain BMPs | May 20, 2015 | Dec 20, 2018 | Resolved |
| cwa | Reporting Violations - Late Submittal of DMRs | May 20, 2015 | Dec 20, 2018 | Resolved |
| cwa | WW Storm Water Non-Construction - Failure to properly install/implement BMPs | Mar 6, 2014 | May 2, 2014 | Resolved |
| cwa | Permit Violations - CWA §308 Failure to submit required permit application information | Mar 6, 2014 | May 2, 2014 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jan 28, 2012 | Dec 31, 2012 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 28, 2009 | — | Open |
Other facilities in YELLOWSTONE County, MT
HI TECH AUTO BODY & PAINT INC
BILLINGS, MT
MT DEPT OF TRANSPORTATION CANYON CREEK 318 PERMIT
BILLINGS, MT
GOLDEN EAGLE WATER USERS ASSN
BILLINGS, MT
SHEPHERD SCHOOLS-TREATMENT PLANT FOR WELL 1 2 3
SHEPHERD, MT
WESTERN PLAINS MACHINERY
BILLINGS, MT
USDOE WAP CUSTER SUBSTATION
CUSTER, MT