HENNEPIN POWER STATION

Quick Summary

  • •Released 248,572 lbs of toxic chemicals to the environment in the most recent TRI reporting year.
  • •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
  • •Assessed $0 in total penalties since records began.
  • •Reports releases of chemicals classified as known or probable carcinogens.
Address
13498 E 800TH ST
HENNEPIN, IL 61327
View on map ↗
County
PUTNAM County
Industry
Utilities
NAICS (North American Industry Classification)
221112
Inspections
1 · last Dec 2, 2021
Total Penalties
$0 · last May 27, 2005
Registry ID
110006166139

How This Compares

#37 of 914 TRI reporters in IL
#192 of 584 TRI reporters in Utilities

Ranked by most recent year's total TRI releases.

Compliance Status (Last 12 Quarters)

Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.

0
Air (CAA)
Qtrs Non-Compliant
8
Water (CWA)
Qtrs Non-Compliant
0
Hazardous Waste (RCRA)
Qtrs Non-Compliant

TRI Toxic Chemical Releases

Annual pounds of each toxic chemical released to air, water, and land, as reported to the EPA Toxic Release Inventory. Carcinogen (♦) and PFAS designations are per EPA and IARC classifications.

Emissions Trend (2015–2019) +62% overall
Year Total Releases (lbs) vs Prior Year
2015 184,677 —
2016 163,071 -12%
2017 248,572 +52%
2018 396,324 +59%
2019 299,298 -24%

2017

Chemical Total (lbs) Air Water Land Off-Site
Barium compounds (except for barium sulfate (CAS No. 7727-43-7)) 207,218 241 470 206,507 —
Hydrogen fluoride 17,132 17,132 — — —
Hydrochloric acid (acid aerosols including mists, vapors, gas, fog, and other airborne forms of any particle size) 13,908 13,908 — — —
Manganese compounds 8,966 47 338 8,581 —
Lead compounds 1,309 17 — 1,292 7
Mercury compounds 39 10 — 29 —
Dioxin and dioxin-like compounds 0 0 — — — ♦ Carcinogen

2016

Chemical Total (lbs) Air Water Land Off-Site
Benzo[g,h,i]perylene — — — — —
Barium compounds (except for barium sulfate (CAS No. 7727-43-7)) 148,755 221 524 148,010 —
Hydrogen fluoride 13,326 13,326 — — —
Lead compounds 964 17 — 947 —
Mercury compounds 25 8 — 16 —
Polycyclic aromatic compounds 1 1 — — — ♦ Carcinogen
Dioxin and dioxin-like compounds 0 0 — — — ♦ Carcinogen

2015

Chemical Total (lbs) Air Water Land Off-Site
Benzo[g,h,i]perylene — — — — —
Barium compounds (except for barium sulfate (CAS No. 7727-43-7)) 162,559 375 638 161,546 —
Hydrogen fluoride 14,016 14,016 — — —
Manganese compounds 6,994 61 412 6,521 —
Lead compounds 1,080 25 — 1,055 2
Mercury compounds 27 9 — 18 3
Polycyclic aromatic compounds 1 1 — — — ♦ Carcinogen
Dioxin and dioxin-like compounds 0 0 — — — ♦ Carcinogen

Waste Management & Recycling

How this facility manages toxic chemicals beyond direct releases — through recycling, energy recovery, and on-site or off-site treatment. Data from the most recent TRI reporting year. Quantities in pounds.

Off-Site Transfer Destinations

Facilities to which toxic chemicals were transferred for disposal, recycling, energy recovery, or treatment during the most recent TRI reporting year. Quantities in pounds.

Destination Chemical Disposal Recycling Energy Rec. Treatment
HERITAGE ENVIRONMENTAL SERVICES (IN)
INDIANAPOLIS, IN
Lead compounds 7 — — —

Compliance Violations

Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.

Program Type Violation Date Return to Compliance Status
cwa Schedule Event achieved late but reported Jan 31, 2026 — Open
cwa Schedule Event achieved late but reported Jul 31, 2025 — Open
cwa Schedule Event unachieved but reported Jul 31, 2025 Sep 13, 2025 Resolved
cwa Schedule Event reported late Jul 31, 2025 — Open
cwa Schedule Event unachieved and not reported Jul 31, 2025 Sep 13, 2025 Resolved
cwa Schedule Event achieved late but reported Jul 31, 2025 — Open
cwa Schedule Event reported late Jul 31, 2023 — Open
cwa Schedule Event unachieved but reported Jul 31, 2023 Sep 6, 2023 Resolved
cwa Schedule Event achieved late but reported Jul 31, 2023 — Open
cwa Schedule Event unachieved and not reported Jul 31, 2023 Sep 6, 2023 Resolved
cwa Schedule Event achieved late but reported Jan 31, 2023 — Open
cwa Schedule Event unachieved but reported Jan 31, 2022 Mar 21, 2022 Resolved
cwa Schedule Event reported late Jan 31, 2022 — Open
cwa Schedule Event achieved late but reported Jan 31, 2022 — Open
cwa Schedule Event unachieved and not reported Jan 31, 2022 Mar 21, 2022 Resolved
cwa Schedule Event unachieved but reported Jan 31, 2022 Mar 21, 2022 Resolved
cwa Schedule Event unachieved and not reported Jan 31, 2022 Mar 21, 2022 Resolved
cwa Schedule Event reported late Jan 31, 2022 — Open
cwa Schedule Event achieved late but reported Jan 31, 2022 — Open
cwa Schedule Event achieved late but reported Jan 31, 2020 — Open
cwa Schedule Event achieved late but reported Jul 31, 2019 — Open
cwa Schedule Event reported late Jul 31, 2019 — Open
cwa Schedule Event unachieved and not reported Jul 31, 2019 Sep 30, 2019 Resolved
cwa Schedule Event unachieved but reported Jul 31, 2019 Sep 30, 2019 Resolved
cwa Schedule Event achieved late but reported Jan 31, 2019 — Open
cwa Schedule Event unachieved and not reported Jan 31, 2016 Mar 24, 2016 Resolved
cwa Schedule Event reported late Jan 31, 2016 — Open
cwa Schedule Event achieved late but reported Jan 31, 2016 — Open
cwa Schedule Event unachieved but reported Jan 31, 2016 Mar 24, 2016 Resolved
cwa Schedule Event reported late Jul 31, 2015 — Open
cwa Schedule Event achieved late but reported Jul 31, 2015 — Open
cwa Schedule Event unachieved and not reported Jul 31, 2015 Mar 24, 2016 Resolved
cwa Schedule Event unachieved but reported Jul 31, 2015 Mar 24, 2016 Resolved
cwa Schedule Event reported late Jul 31, 2014 — Open
cwa Schedule Event unachieved but reported Jul 31, 2014 Mar 24, 2016 Resolved
cwa Schedule Event achieved late but reported Jul 31, 2014 — Open
cwa Schedule Event unachieved and not reported Jul 31, 2014 Mar 24, 2016 Resolved
cwa Schedule Event reported late Jan 31, 2010 — Open
cwa Schedule Event unachieved and not reported Jan 31, 2010 Mar 4, 2010 Resolved
cwa Schedule Event achieved late but reported Jan 31, 2010 — Open
cwa Schedule Event unachieved but reported Jan 31, 2010 Mar 4, 2010 Resolved
cwa Schedule Event achieved late but reported Jul 31, 2009 — Open
cwa Schedule Event reported late Jan 31, 2009 — Open
cwa Schedule Event achieved late but reported Jan 31, 2009 — Open
cwa Schedule Event unachieved but reported Jan 31, 2009 Mar 6, 2009 Resolved
cwa Schedule Event achieved late but reported Jan 31, 2009 — Open
cwa Schedule Event reported late Jan 31, 2009 — Open
cwa Schedule Event unachieved and not reported Jan 31, 2009 Jun 30, 2009 Resolved
cwa Schedule Event unachieved and not reported Jan 31, 2009 Mar 6, 2009 Resolved
cwa Schedule Event unachieved but reported Jan 31, 2009 Jun 30, 2009 Resolved

Enforcement Actions

Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.

Judicial
· Case 05-1999-0751 · May 27, 2005
$9,000,000
Administrative - Formal
· Case 05-1992-0053 · Sep 1, 1993
$12,500
Civil Judicial Action
Clean Water Act · Case IL-N00001507 · Mar 2, 1989

Other facilities in PUTNAM County, IL