CJ TMI MANUFACTURING AMERICA, LLC
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $18,000 in total penalties since records began.
- Address
-
2 APPLEGATE DR.
ROBBINSVILLE TWP, NJ 08691
View on map ↗ - County
- MERCER County
- Industry
- Manufacturing
- NAICS (North American Industry Classification)
- 311412
- Total Penalties
- $18,000 · last May 13, 2025
- Registry ID
- 110070213939
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | WW Storm Water Non-Construction - Failure to Conduct Inspections | Jun 18, 2025 | — | Open |
| cwa | Schedule Event reported late | May 13, 2025 | — | Open |
| cwa | Schedule Event achieved late but reported | May 13, 2025 | — | Open |
| cwa | Schedule Event reported late | May 13, 2025 | — | Open |
| cwa | Schedule Event achieved late but reported | May 13, 2025 | — | Open |
| cwa | WW Storm Water Non-Construction - Failure to Implement SWPPP/SWMP | Jun 18, 2024 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jun 30, 2023 | Jul 31, 2023 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jun 30, 2023 | Jul 31, 2023 | Resolved |
| cwa | WW Storm Water Non-Construction - Failure to Conduct Inspections | Apr 24, 2023 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jul 4, 2022 | Aug 4, 2022 | Resolved |
| cwa | Schedule Event unachieved and not reported | Apr 1, 2018 | May 2, 2018 | Resolved |
| cwa | Schedule Event unachieved and not reported | Apr 1, 2018 | May 2, 2018 | Resolved |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| Temperature, water deg. centigrade | DMR, Limited - Numeric Violation | 2,970.00 deg C | 65.00 | +4,469% | Sep 2025 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 553.43 kg/d | 513.38 | +8% | May 2024 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 773.16 kg/d | 513.38 | +51% | Feb 2024 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 1,015.60 kg/d | 513.38 | +98% | Oct 2023 | Open |
| Oil & Grease | DMR, Limited - Numeric Violation | 134.00 mg/L | 100.00 | +34% | Oct 2023 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 980.19 kg/d | 390.44 | +151% | Jan 2022 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 449.04 kg/d | 390.44 | +15% | Apr 2021 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 416.02 kg/d | 390.44 | +7% | Aug 2020 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 395.43 kg/d | 390.44 | +1% | May 2019 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Overdue | 518.47 kg/d | 390.44 | +33% | Feb 2019 | Resolved |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 518.47 kg/d | 390.44 | +33% | Feb 2019 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 496.68 kg/d | 390.44 | +27% | Jan 2019 | Open |
Enforcement Actions