Non-Compliance
Clean Water Act
FERNDALE SEWAGE TREATMENT PLANT (STP)
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
5405 FERNDALE RD
FERNDALE, WA 98248
View on map ↗ - County
- WHATCOM County
- Inspections
- 3 · last Jul 3, 2025
- Total Penalties
- $0
- Registry ID
- 110006684267
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
12
Water (CWA)
Qtrs Non-Compliant
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event unachieved and not reported | Jul 30, 2023 | Aug 30, 2023 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jul 30, 2023 | Aug 30, 2023 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jan 30, 2021 | Mar 2, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jan 30, 2021 | Mar 2, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jan 30, 2021 | Mar 2, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jan 30, 2021 | Mar 2, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Sep 1, 2020 | Oct 2, 2020 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2020 | May 1, 2020 | Resolved |
| cwa | Schedule Event unachieved and not reported | Dec 1, 2019 | Mar 1, 2020 | Resolved |
| cwa | Schedule Event reported late | Sep 1, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Sep 1, 2018 | — | Open |
| cwa | Schedule Event unachieved but reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jul 30, 2018 | Aug 30, 2018 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jul 30, 2018 | Aug 30, 2018 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jul 30, 2018 | Aug 30, 2018 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event reported late | Jul 30, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event unachieved but reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event reported late | Jul 30, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event unachieved but reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event reported late | Jul 30, 2018 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event unachieved but reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event reported late | Jul 30, 2018 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event unachieved but reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event reported late | Jul 30, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event reported late | Jul 30, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event unachieved but reported | Jul 30, 2018 | Oct 1, 2018 | Resolved |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 30, 2018 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2018 | May 1, 2018 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jan 1, 2018 | Feb 1, 2018 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jan 1, 2018 | Apr 2, 2018 | Resolved |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| Chlorine, total residual | DMR, Limited - Numeric Violation | 0.03 mg/L | 0.03 | +99,999% | Oct 2025 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 35.67 mg/L | 30.00 | +19% | Jul 2021 | Open |
Other facilities in WHATCOM County, WA
IDIOM THEATRE
BELLINGHAM, WA
· Real Estate and Rental and Leasing
LISTER CHAIN AND FORGE INC
BLAINE, WA
· Manufacturing
STORYBROOK PARK PHASE 1
BELLINGHAM, WA