PLANT CITY WRF
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $76,707 in total penalties since records began.
- Address
-
1500 W. VICTORIA STREET
PLANT CITY, FL 33563
View on map ↗ - County
- HILLSBOROUGH County
- Industry
- Public Administration
- NAICS (North American Industry Classification)
- 924110
- Inspections
- 9 · last Apr 2, 2025
- Total Penalties
- $76,707 · last May 14, 2025
- Registry ID
- 110035612539
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
Qtrs Non-Compliant
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | WW SSO - Discharge to Waters | Feb 17, 2026 | — | Open |
| cwa | WW SSO - Discharge to Waters | Jan 22, 2026 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Dec 12, 2025 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Oct 5, 2025 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Sep 24, 2025 | — | Open |
| cwa | WW SSO - Discharge to Waters | Sep 22, 2025 | — | Open |
| cwa | WW SSO - Discharge to Waters | May 30, 2025 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | May 20, 2025 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Apr 24, 2025 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Apr 10, 2025 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Jan 26, 2025 | — | Open |
| cwa | WW SSO - Discharge to Waters | Oct 27, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Oct 10, 2024 | — | Open |
| cwa | WW SSO - Discharge to Waters | Oct 10, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Oct 8, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Sep 25, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Sep 20, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Aug 29, 2024 | — | Open |
| cwa | WW SSO - Discharge to Waters | Aug 6, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Aug 6, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Aug 5, 2024 | — | Open |
| cwa | WW SSO - Discharge to Waters | Aug 5, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Jun 21, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Jun 10, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | May 17, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | May 15, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Apr 4, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Mar 26, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Mar 3, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Feb 21, 2024 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Dec 11, 2023 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Nov 2, 2023 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Jul 18, 2023 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Jul 11, 2023 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Nov 22, 2022 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Mar 21, 2022 | — | Open |
| cwa | WW SSO - Discharge to Waters | Feb 9, 2022 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Jun 22, 2021 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Jan 19, 2021 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | May 6, 2020 | — | Open |
| cwa | Effluent Violations - Narrative Effluent Violation | Feb 10, 2020 | — | Open |
| cwa | Effluent Violations - Narrative Effluent Violation | Aug 28, 2019 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Aug 14, 2019 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Jul 29, 2019 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Jul 22, 2019 | — | Open |
| cwa | WW SSO - Overflow to Dry Land or Building Backup | Oct 20, 2018 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 13, 2004 | — | Open |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| IC25 Static Renewal 7 Day Chronic Ceriodaphnia dubia | DMR, Limited - Numeric Violation | 100.00 % | 100.00 | +99,999% | Jan 2026 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 13.00 mg/L | 10.00 | +30% | Dec 2025 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 11.00 mg/L | 10.00 | +10% | Apr 2025 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 150.00 mg/L | 10.00 | +1,400% | Oct 2024 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 11.07 mg/L | 7.50 | +48% | Oct 2024 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 40.12 mg/L | 6.25 | +542% | Oct 2024 | Open |
| Nitrogen, total [as N] | DMR, Limited - Numeric Violation | 7.20 mg/L | 6.00 | +20% | Jul 2023 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 3.50 mg/L | 2.00 | +75% | Oct 2022 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 200.00 MPN/100mL | 86.00 | +133% | Oct 2022 | Open |
| Nitrogen, total [as N] | DMR, Limited - Numeric Violation | 6.78 mg/L | 6.00 | +13% | Jun 2022 | Open |
| Nitrogen, total [as N] | DMR, Limited - Numeric Violation | 6.41 mg/L | 6.00 | +7% | May 2022 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 4.67 MGD | 4.50 | +4% | May 2020 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 4.70 MGD | 4.50 | +4% | Apr 2020 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 4.73 MGD | 4.50 | +5% | Mar 2020 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 4.85 MGD | 4.50 | +8% | Feb 2020 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 4.92 MGD | 4.50 | +9% | Jan 2020 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 5.05 MGD | 4.50 | +12% | Dec 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 5.12 MGD | 4.50 | +14% | Nov 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 5.07 MGD | 4.50 | +13% | Oct 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 5.07 MGD | 4.50 | +13% | Sep 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 5.19 MGD | 4.50 | +15% | Aug 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 5.09 MGD | 4.50 | +13% | Jul 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 5.14 MGD | 4.50 | +14% | Jun 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 5.04 MGD | 4.50 | +12% | May 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 5.10 MGD | 4.50 | +13% | Apr 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 4.86 MGD | 4.50 | +8% | Mar 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 4.54 MGD | 4.50 | +1% | Feb 2019 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 3.80 MGD | 3.68 | +3% | Aug 2018 | Open |
| Nitrogen, total [as N] | DMR, Limited - Numeric Violation | 11.57 mg/L | 6.00 | +93% | Apr 2018 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 2.25 mg/L | 1.50 | +50% | Apr 2018 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.45 mg/L | 1.25 | +16% | Apr 2018 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 6.15 mg/L | 2.00 | +208% | Apr 2018 | Open |
| Nitrogen, total [as N] | DMR, Limited - Numeric Violation | 4.61 mg/L | 4.50 | +2% | Sep 2017 | Open |
| Nitrogen, total [as N] | DMR, Limited - Numeric Violation | 8.24 mg/L | 6.00 | +37% | Sep 2017 | Open |
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 10.10 mg/L | 10.00 | +1% | Dec 2016 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 20.00 mg/L | 10.00 | +100% | Nov 2016 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 10.00 mg/L | 7.50 | +33% | Nov 2016 | Open |
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 8.34 mg/L | 7.50 | +11% | Nov 2016 | Open |
| BOD, carbonaceous [5 day, 20 C] | DMR, Limited - Numeric Violation | 19.60 mg/L | 10.00 | +96% | Nov 2016 | Open |
| Nitrogen, total [as N] | DMR, Limited - Numeric Violation | 10.04 mg/L | 6.00 | +67% | Sep 2016 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 2.74 MGD | 2.68 | +2% | Dec 2015 | Open |
| Nitrogen, total [as N] | DMR, Limited - Numeric Violation | 6.40 mg/L | 6.00 | +7% | Nov 2015 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 2.87 MGD | 2.68 | +7% | Nov 2015 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 2.95 MGD | 2.68 | +10% | Oct 2015 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 3.07 MGD | 2.68 | +15% | Sep 2015 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 3.12 MGD | 2.68 | +17% | Aug 2015 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 2.91 MGD | 2.68 | +8% | Jul 2015 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 3.03 MGD | 2.68 | +13% | Jun 2015 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 3.18 MGD | 2.68 | +19% | May 2015 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 3.17 MGD | 2.68 | +18% | Apr 2015 | Open |
Enforcement Actions
Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.