Non-Compliance
Clean Water Act
MILTON WWTF
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
DOCK STREET
MILTON, NY 12547
View on map ↗ - County
- ULSTER County
- Inspections
- 4 · last May 21, 2025
- Total Penalties
- $0
- Registry ID
- 110009823959
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
4
Water (CWA)
Qtrs Non-Compliant
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event unachieved and not reported | Mar 28, 2025 | Aug 5, 2025 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 28, 2025 | Aug 5, 2025 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 28, 2025 | — | Open |
| cwa | Schedule Event reported late | Mar 28, 2025 | — | Open |
| cwa | Schedule Event reported late | Mar 28, 2024 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 28, 2024 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 28, 2024 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 28, 2024 | — | Open |
| cwa | Schedule Event unachieved and not reported | Aug 1, 2021 | Aug 10, 2022 | Resolved |
| cwa | Schedule Event unachieved but reported | Aug 1, 2021 | Dec 1, 2021 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 1, 2021 | — | Open |
| cwa | Schedule Event reported late | Aug 1, 2021 | — | Open |
| cwa | Schedule Event unachieved and not reported | Aug 1, 2020 | Nov 1, 2021 | Resolved |
| cwa | Schedule Event unachieved but reported | Aug 1, 2020 | Nov 1, 2021 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 1, 2020 | — | Open |
| cwa | Schedule Event reported late | Aug 1, 2020 | — | Open |
| cwa | Schedule Event reported late | Mar 28, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 28, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Feb 1, 2020 | — | Open |
| cwa | Schedule Event unachieved but reported | Feb 1, 2020 | Jan 31, 2021 | Resolved |
| cwa | Schedule Event unachieved and not reported | Feb 1, 2020 | Jan 31, 2021 | Resolved |
| cwa | Schedule Event reported late | Feb 1, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 28, 2018 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 28, 2018 | Mar 22, 2019 | Resolved |
| cwa | Schedule Event reported late | Mar 28, 2018 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 28, 2018 | Mar 22, 2019 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 28, 2017 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 28, 2014 | Jul 14, 2014 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 28, 2014 | Jul 14, 2014 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 28, 2014 | — | Open |
| cwa | Schedule Event reported late | Mar 28, 2014 | — | Open |
| cwa | Schedule Event reported late | Mar 28, 2013 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 28, 2013 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 28, 2013 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 28, 2013 | — | Open |
| cwa | Schedule Event reported late | Mar 28, 2012 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 28, 2012 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 28, 2012 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 28, 2012 | — | Open |
| cwa | Schedule Event reported late | Mar 28, 2011 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 28, 2011 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 28, 2011 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 28, 2011 | — | Open |
| cwa | Schedule Event reported late | Mar 28, 2010 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 28, 2010 | Sep 1, 2010 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 28, 2010 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 28, 2010 | Sep 1, 2010 | Resolved |
| cwa | Schedule Event reported late | Mar 28, 2009 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 28, 2009 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 28, 2009 | — | Open |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 83.00 % | 85.00 | +13% | Mar 2022 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 84.00 % | 85.00 | +7% | Jan 2022 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 438.30 MPN/100mL | 200.00 | +119% | Mar 2021 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 438.30 MPN/100mL | 400.00 | +10% | Mar 2021 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 39.00 mg/L | 30.00 | +30% | Nov 2019 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 81.00 % | 85.00 | +27% | Nov 2019 | Open |
| Solids, settleable | DMR, Limited - Numeric Violation | 0.00 mg/L | 0.00 | +233% | May 2017 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 84.00 % | 85.00 | +7% | Mar 2017 | Open |
| Flow, in conduit or thru treatment plant | DMR, Limited - Numeric Violation | 0.31 MGD | 0.06 | +464% | Mar 2017 | Open |
Other facilities in ULSTER County, NY
NOCO DISTRIBUTING
KINGSTON, NY
· Wholesale Trade
PARVENU INC
ELLENVILLE, NY
HUDSON VALLEY WATER CO #5-TREATMENT PLANT
WOODBURY, NY
HORSE SHOW FACILITY
SAUGERTIES, NY
MOUNTAIN VIEW MARKET-ULTRAVIOLET RADIATION
SAUGERTIES, NY