POTSDAM (V) WPCP
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
OUTER CHERRY STREET
POTSDAM, NY 13676
View on map ↗ - County
- SAINT LAWRENCE County
- Inspections
- 5 · last Oct 9, 2025
- Total Penalties
- $0
- Registry ID
- 110006621423
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event reported late | Aug 1, 2024 | — | Open |
| cwa | Schedule Event unachieved and not reported | Aug 1, 2024 | Sep 16, 2024 | Resolved |
| cwa | Schedule Event unachieved but reported | Aug 1, 2024 | Sep 16, 2024 | Resolved |
| cwa | Schedule Event achieved late but reported | Aug 1, 2024 | — | Open |
| cwa | Schedule Event unachieved but reported | Aug 1, 2023 | Oct 10, 2023 | Resolved |
| cwa | Schedule Event unachieved and not reported | Aug 1, 2023 | Oct 10, 2023 | Resolved |
| cwa | Schedule Event reported late | Aug 1, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 1, 2023 | — | Open |
| cwa | Schedule Event reported late | Feb 28, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Feb 28, 2023 | — | Open |
| cwa | Schedule Event unachieved but reported | Feb 28, 2023 | Apr 19, 2023 | Resolved |
| cwa | Schedule Event unachieved and not reported | Feb 28, 2023 | Apr 19, 2023 | Resolved |
| cwa | Schedule Event reported late | Aug 1, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | Aug 1, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | May 30, 2021 | Dec 2, 2021 | Resolved |
| cwa | Schedule Event achieved late but reported | May 30, 2021 | — | Open |
| cwa | Schedule Event unachieved but reported | May 30, 2021 | Dec 2, 2021 | Resolved |
| cwa | Schedule Event reported late | May 30, 2021 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 31, 2020 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 31, 2016 | — | Open |
| cwa | Schedule Event reported late | Jan 31, 2008 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 31, 2008 | — | Open |
| cwa | Schedule Event unachieved but reported | Oct 24, 2007 | May 30, 2008 | Resolved |
| cwa | Schedule Event achieved late but reported | Oct 24, 2007 | — | Open |
| cwa | Schedule Event reported late | Oct 24, 2007 | — | Open |
| cwa | Schedule Event unachieved and not reported | Oct 24, 2007 | May 30, 2008 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 28, 2007 | Jul 26, 2007 | Resolved |
| cwa | Schedule Event reported late | Mar 28, 2007 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 28, 2007 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 28, 2007 | Jul 26, 2007 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 31, 2007 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 31, 2006 | — | Open |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 83.59 % | 85.00 | +9% | Jan 2026 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.15 mg/L | 1.00 | +15% | Dec 2025 | Resolved |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.09 mg/L | 1.00 | +9% | Nov 2025 | Resolved |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 2.05 mg/L | 1.00 | +105% | Oct 2025 | Resolved |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.51 mg/L | 1.00 | +51% | Sep 2025 | Resolved |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.60 mg/L | 1.00 | +60% | Aug 2025 | Resolved |
| Solids, settleable | DMR, Limited - Numeric Violation | 0.00 mg/L | 0.00 | +400% | Aug 2025 | Resolved |
| Solids, settleable | DMR, Limited - Numeric Violation | 0.00 mg/L | 0.00 | +133% | Jul 2025 | Resolved |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.36 mg/L | 1.00 | +36% | Jul 2025 | Resolved |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.63 mg/L | 1.00 | +63% | Feb 2025 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.26 mg/L | 1.00 | +26% | Nov 2024 | Open |
| Solids, settleable | DMR, Limited - Numeric Violation | 0.00 mg/L | 0.00 | +367% | Sep 2024 | Open |
| Solids, settleable | DMR, Limited - Numeric Violation | 0.04 mg/L | 0.00 | +11,567% | Feb 2024 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 83.79 % | 85.00 | +8% | Feb 2024 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 83.42 % | 85.00 | +11% | Jan 2024 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.05 mg/L | 1.00 | +5% | Nov 2023 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.10 mg/L | 1.00 | +10% | Oct 2023 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 1.35 mg/L | 1.00 | +35% | Sep 2023 | Open |
| Phosphorus, total [as P] | DMR, Limited - Overdue | 1.35 mg/L | 1.00 | +35% | Sep 2023 | Resolved |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 1,780.00 MPN/100mL | 400.00 | +345% | Oct 2022 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 2,400.00 MPN/100mL | 400.00 | +500% | Sep 2022 | Open |
| Solids, settleable | DMR, Limited - Numeric Violation | 0.05 mg/L | 0.00 | +16,567% | Feb 2022 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 73.83 % | 85.00 | +74% | Dec 2021 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 79.57 % | 85.00 | +36% | Nov 2021 | Open |
| Solids, settleable | DMR, Limited - Numeric Violation | 0.00 mg/L | 0.00 | +233% | Mar 2020 | Open |
| Solids, settleable | DMR, Limited - Numeric Violation | 0.03 mg/L | 0.00 | +8,233% | May 2019 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 83.30 % | 85.00 | +11% | Jan 2019 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Overdue | 84.10 % | 85.00 | +6% | Dec 2018 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 84.10 % | 85.00 | +6% | Dec 2018 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 276.00 MPN/100mL | 200.00 | +38% | Sep 2018 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 1,056.00 MPN/100mL | 400.00 | +164% | Sep 2018 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 81.48 % | 85.00 | +23% | Jan 2017 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 81.79 % | 85.00 | +21% | Dec 2015 | Open |
| Solids, settleable | DMR, Limited - Numeric Violation | 0.00 mg/L | 0.00 | +33% | Jul 2015 | Open |
Enforcement Actions
Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.