TROY STP, CITY OF
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
ILLINOIS ROUTE 162
TROY, IL 62294
View on map ↗ - County
- MADISON County
- Inspections
- 2 · last May 19, 2025
- Total Penalties
- $0 · last Jun 18, 1998
- Registry ID
- 110006368082
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Jul 21, 2025 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Apr 19, 2025 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Apr 5, 2025 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Apr 5, 2025 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Apr 4, 2025 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Apr 4, 2025 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Apr 4, 2025 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Apr 4, 2025 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Apr 4, 2025 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Apr 4, 2025 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Apr 4, 2025 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Apr 4, 2025 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 31, 2025 | Sep 8, 2025 | Resolved |
| cwa | Schedule Event reported late | Mar 31, 2025 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 31, 2025 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2025 | Sep 8, 2025 | Resolved |
| cwa | Dry-weather SSO, no discharge to waters of the U.S., that may endanger health or the environment | Dec 4, 2024 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Nov 5, 2024 | — | Open |
| cwa | Wet-weather unanticipated prohibited bypass discharge to waters of the U.S. - endangerment | Nov 5, 2024 | — | Open |
| cwa | Schedule Event unachieved but reported | Jul 31, 2024 | Feb 28, 2025 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jul 31, 2024 | Feb 28, 2025 | Resolved |
| cwa | Schedule Event reported late | Jul 31, 2024 | — | Open |
| cwa | Schedule Event achieved late but reported | Jul 31, 2024 | — | Open |
| cwa | Schedule Event reported late | Mar 31, 2024 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2024 | Aug 20, 2024 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 31, 2024 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 31, 2024 | Aug 20, 2024 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 31, 2023 | — | Open |
| cwa | Schedule Event reported late | Jan 31, 2023 | — | Open |
| cwa | Schedule Event unachieved but reported | Sep 30, 2022 | Dec 5, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Sep 30, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | Sep 30, 2022 | Dec 5, 2022 | Resolved |
| cwa | Schedule Event unachieved and not reported | Sep 30, 2022 | Dec 5, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Sep 30, 2022 | — | Open |
| cwa | Schedule Event unachieved but reported | Sep 30, 2022 | Dec 5, 2022 | Resolved |
| cwa | Schedule Event reported late | Sep 30, 2022 | — | Open |
| cwa | Schedule Event reported late | Sep 30, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 31, 2022 | — | Open |
| cwa | Schedule Event reported late | Mar 31, 2022 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 31, 2022 | May 26, 2022 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2022 | May 26, 2022 | Resolved |
| cwa | Schedule Event reported late | Mar 31, 2021 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 31, 2021 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2021 | May 24, 2022 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 31, 2021 | May 24, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Jan 31, 2019 | — | Open |
| cwa | Schedule Event achieved late but reported | Jan 19, 2018 | — | Open |
| cwa | Effluent Violations - Unapproved Bypass | May 6, 2017 | Jun 14, 2017 | Resolved |
| cwa | Effluent Violations - Unauthorized Discharge | May 6, 2017 | Jun 14, 2017 | Resolved |
| cwa | Schedule Event reported late | May 31, 2016 | — | Open |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.09 mg/L | 0.05 | +74% | Dec 2022 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.78 kg/d | 0.77 | +1% | Dec 2022 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.05 mg/L | 0.05 | +1% | Feb 2022 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.04 mg/L | 0.03 | +16% | Jan 2022 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.07 mg/L | 0.05 | +30% | Jan 2022 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.03 mg/L | 0.03 | +7% | Sep 2020 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.04 mg/L | 0.03 | +17% | Dec 2019 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.03 mg/L | 0.03 | +7% | Nov 2019 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.03 mg/L | 0.03 | +10% | Oct 2019 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.77 kg/d | 0.68 | +13% | Mar 2018 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.03 mg/L | 0.03 | +3% | Dec 2017 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.04 mg/L | 0.03 | +27% | Nov 2017 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.07 mg/L | 0.05 | +57% | Nov 2017 | Open |
| Copper, total [as Cu] | DMR, Limited - Numeric Violation | 0.03 mg/L | 0.03 | +3% | Oct 2017 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 400.00 MPN/100mL | 400.00 | +99,999% | Jul 2016 | Open |
Enforcement Actions
Formal enforcement cases brought by the EPA or state agencies, including administrative orders and civil penalties assessed. Penalty amounts reflect what was formally assessed, not necessarily what was collected.