EmissionsLookup
Non-Compliance Clean Water Act

FCPWSD #3 PINE LAKE ESTATES WWTP

Quick Summary

  • Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
  • Assessed $0 in total penalties since records began.
Address
HWY M
GRAY SUMMIT, MO 63039
View on map ↗
County
FRANKLIN County
Inspections
1 · last Apr 7, 2022
Total Penalties
$0
Registry ID
110042679777

Compliance Status (Last 12 Quarters)

Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.

2
Water (CWA)
Qtrs Non-Compliant

Compliance Violations

Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.

Program Type Violation Date Return to Compliance Status
cwa Reporting Violations - Failure to Submit DMRs Nov 20, 2023 Open
cwa Effluent Violations - Numeric effluent violation Sep 28, 2023 Nov 17, 2023 Resolved
cwa Effluent Violations - Numeric effluent violation Apr 4, 2023 Apr 19, 2023 Resolved
cwa Effluent Violations - Numeric effluent violation Oct 19, 2022 Oct 21, 2022 Resolved
cwa Management Practice Violations - Improper Operation and Maintenance Apr 26, 2022 Jun 3, 2022 Resolved
cwa Effluent Violations - Numeric effluent violation Apr 26, 2022 Jun 3, 2022 Resolved
cwa Effluent Violations - Numeric effluent violation Apr 4, 2022 Apr 8, 2022 Resolved
cwa Schedule Event reported late Sep 1, 2019 Open
cwa Schedule Event unachieved and not reported Sep 1, 2019 Oct 7, 2019 Resolved
cwa Schedule Event achieved late but reported Sep 1, 2019 Open
cwa Schedule Event unachieved but reported Sep 1, 2019 Oct 7, 2019 Resolved
cwa Schedule Event unachieved and not reported Aug 5, 2011 Oct 5, 2011 Resolved
cwa Schedule Event achieved late but reported Aug 5, 2011 Open
cwa Schedule Event reported late Aug 5, 2011 Open
cwa Schedule Event unachieved but reported Aug 5, 2011 Oct 5, 2011 Resolved
cwa Schedule Event unachieved but reported Feb 5, 2011 Jun 13, 2011 Resolved
cwa Schedule Event achieved late but reported Feb 5, 2011 Open
cwa Schedule Event reported late Feb 5, 2011 Open
cwa Schedule Event unachieved and not reported Feb 5, 2011 Jun 13, 2011 Resolved

Discharge Limit Exceedances

Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.

Pollutant Violation Reported Limit Exceedance Period Status
E. coli DMR, Limited - Numeric Violation 1,300.00 MPN/100mL 1,030.00 +26% Dec 2025 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 22.01 mg/L 8.40 +162% Dec 2025 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 22.01 mg/L 2.20 +900% Dec 2025 Open
E. coli DMR, Limited - Numeric Violation 6,000.00 MPN/100mL 1,030.00 +483% Dec 2023 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 34.91 mg/L 10.10 +246% Jun 2023 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 12.10 mg/L 1.50 +707% Jun 2023 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 24.60 mg/L 2.20 +1,018% Dec 2022 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 24.60 mg/L 8.40 +193% Dec 2022 Open
E. coli DMR, Limited - Numeric Violation 2,419.60 MPN/100mL 1,030.00 +135% Jun 2022 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 22.40 mg/L 12.10 +85% Dec 2021 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 21.55 mg/L 2.40 +798% Dec 2021 Open
Nitrogen, ammonia total [as N] DMR, Limited - Numeric Violation 1.24 mg/L 1.10 +13% Sep 2021 Open

Other facilities in FRANKLIN County, MO

PARKER HANNIFIN SPORLAN DIV - PLANT #2
WASHINGTON, MO · Manufacturing
WILLOW GROVE
OAK GROVE, MO
WEG TRANSFORMERS USA LLC
WASHINGTON, MO · Manufacturing
SIESCO VALLEY SCREW PRODUCTS
UNION, MO · Manufacturing
All facilities in MO →