Non-Compliance
Clean Water Act
CALICHE WATER AND WASTEWATER TREATMENT PLANT
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
26308 CR 65
ILIFF, CO 80736
View on map ↗ - County
- LOGAN County
- Inspections
- 2 · last Sep 14, 2022
- Total Penalties
- $0
- Registry ID
- 110070675044
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
10
Water (CWA)
Qtrs Non-Compliant
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event achieved late but reported | Dec 31, 2023 | — | Open |
| cwa | Schedule Event unachieved but reported | Dec 31, 2023 | Nov 26, 2024 | Resolved |
| cwa | Schedule Event reported late | Dec 31, 2023 | — | Open |
| cwa | Schedule Event unachieved but reported | Dec 31, 2023 | Apr 3, 2024 | Resolved |
| cwa | Schedule Event unachieved and not reported | Dec 31, 2023 | Nov 26, 2024 | Resolved |
| cwa | Schedule Event unachieved and not reported | Dec 31, 2023 | Apr 3, 2024 | Resolved |
| cwa | Schedule Event reported late | Dec 31, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Dec 31, 2023 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jun 30, 2023 | Oct 24, 2023 | Resolved |
| cwa | Schedule Event reported late | Jun 30, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Jun 30, 2023 | — | Open |
| cwa | Schedule Event unachieved but reported | Jun 30, 2023 | Oct 24, 2023 | Resolved |
| cwa | Schedule Event reported late | Jun 30, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jun 30, 2022 | Oct 24, 2023 | Resolved |
| cwa | Schedule Event achieved late but reported | Jun 30, 2022 | — | Open |
| cwa | Schedule Event unachieved but reported | Jun 30, 2022 | Oct 24, 2023 | Resolved |
| cwa | Schedule Event unachieved and not reported | Jun 30, 2021 | Oct 24, 2023 | Resolved |
| cwa | Schedule Event unachieved but reported | Jun 30, 2021 | Oct 24, 2023 | Resolved |
| cwa | Schedule Event achieved late but reported | Jun 30, 2021 | — | Open |
| cwa | Schedule Event reported late | Jun 30, 2021 | — | Open |
| cwa | Schedule Event achieved late but reported | Jun 30, 2020 | — | Open |
| cwa | Schedule Event unachieved but reported | Jun 30, 2020 | Oct 24, 2023 | Resolved |
| cwa | Schedule Event reported late | Jun 30, 2020 | — | Open |
| cwa | Schedule Event unachieved and not reported | Jun 30, 2020 | Oct 24, 2023 | Resolved |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 77.00 % | 85.00 | +53% | Jan 2026 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 65.00 mg/L | 45.00 | +44% | Jan 2026 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 65.00 mg/L | 30.00 | +117% | Jan 2026 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 10.90 mg/L | 1.60 | +581% | Jan 2026 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 51.00 mg/L | 30.00 | +70% | Dec 2025 | Resolved |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 8.90 mg/L | 1.60 | +456% | Dec 2025 | Resolved |
| Solids, total suspended | DMR, Limited - Numeric Violation | 51.00 mg/L | 45.00 | +13% | Dec 2025 | Open |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 50.00 % | 85.00 | +233% | Dec 2025 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 9.43 mg/L | 1.60 | +489% | Nov 2025 | Resolved |
| Solids, total suspended | DMR, Limited - Numeric Violation | 35.00 mg/L | 30.00 | +17% | Nov 2025 | Resolved |
| Solids, total suspended | DMR, Limited - Numeric Violation | 138.00 mg/L | 30.00 | +360% | Oct 2025 | Resolved |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 9.53 mg/L | 1.60 | +496% | Oct 2025 | Resolved |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 60.00 % | 85.00 | +167% | Oct 2025 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 138.00 mg/L | 45.00 | +207% | Oct 2025 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 161.00 mg/L | 30.00 | +437% | Sep 2025 | Resolved |
| Solids, total suspended | DMR, Limited - Numeric Violation | 161.00 mg/L | 45.00 | +258% | Sep 2025 | Open |
| BOD, 5-day, 20 deg. C | DMR, Limited - Numeric Violation | 34.00 mg/L | 30.00 | +13% | Sep 2025 | Open |
| Phosphorus, total [as P] | DMR, Limited - Numeric Violation | 6.22 mg/L | 1.60 | +289% | Sep 2025 | Resolved |
| Solids, suspended percent removal | DMR, Limited - Numeric Violation | 0.00 % | 85.00 | +567% | Sep 2025 | Open |
| BOD, 5-day, percent removal | DMR, Limited - Numeric Violation | 82.00 % | 85.00 | +20% | Sep 2025 | Open |
Other facilities in LOGAN County, CO
MCATEE CONSTRUCTION CO- RIVERSIDE
STERLING, CO
· Manufacturing
MCENDAFFER FEEDYARD
MERINO, CO
STERLING HAULING FACILITY AND TRANSFER STATION
UNINCORPORATED, CO
MERINO TOWN OF
MERINO, CO
KUES GRAVEL PIT
LOGAN COUNTY, CO