Non-Compliance
Clean Water Act
METALINE STP
Quick Summary
- •Currently out of compliance in at least one environmental program (CAA, CWA, or RCRA).
- •Assessed $0 in total penalties since records began.
- Address
-
WA-31
METALINE, WA 99152
View on map ↗ - County
- PEND OREILLE County
- Inspections
- 1 · last Mar 11, 2026
- Total Penalties
- $0
- Registry ID
- 110055005836
Compliance Status (Last 12 Quarters)
Number of calendar quarters, out of the last 12, in which this facility was in violation of its permit. Zero means no recorded violations in that program over the past three years.
12
Water (CWA)
Qtrs Non-Compliant
Qtrs Non-Compliant
Compliance Violations
Individual permit violations recorded by the EPA across air, water, and hazardous waste programs. Open violations are unresolved as of the most recent ECHO data update.
| Program | Type | Violation Date | Return to Compliance | Status |
|---|---|---|---|---|
| cwa | Schedule Event achieved late but reported | Mar 31, 2025 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 31, 2025 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2025 | May 5, 2025 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 31, 2025 | May 5, 2025 | Resolved |
| cwa | Schedule Event reported late | Mar 31, 2025 | — | Open |
| cwa | Schedule Event reported late | May 31, 2024 | — | Open |
| cwa | Schedule Event unachieved and not reported | May 31, 2024 | Sep 12, 2024 | Resolved |
| cwa | Schedule Event achieved late but reported | May 31, 2024 | — | Open |
| cwa | Schedule Event unachieved but reported | May 31, 2024 | Sep 12, 2024 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 31, 2024 | — | Open |
| cwa | Schedule Event reported late | Mar 31, 2024 | — | Open |
| cwa | Schedule Event reported late | Mar 31, 2024 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 31, 2024 | — | Open |
| cwa | Schedule Event achieved late but reported | May 31, 2023 | — | Open |
| cwa | Schedule Event reported late | May 31, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 31, 2023 | — | Open |
| cwa | Schedule Event reported late | Mar 31, 2023 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 31, 2023 | — | Open |
| cwa | Schedule Event unachieved and not reported | Dec 31, 2022 | May 15, 2023 | Resolved |
| cwa | Schedule Event unachieved but reported | Dec 31, 2022 | May 15, 2023 | Resolved |
| cwa | Schedule Event reported late | Dec 31, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | Dec 31, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | Sep 30, 2022 | Jan 4, 2023 | Resolved |
| cwa | Schedule Event unachieved and not reported | Sep 30, 2022 | Oct 31, 2022 | Resolved |
| cwa | Schedule Event unachieved but reported | Sep 30, 2022 | Jan 4, 2023 | Resolved |
| cwa | Schedule Event reported late | Sep 30, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | Sep 30, 2022 | — | Open |
| cwa | Schedule Event reported late | May 31, 2022 | — | Open |
| cwa | Schedule Event reported late | May 31, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | May 31, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | May 31, 2022 | — | Open |
| cwa | Schedule Event reported late | Mar 31, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 31, 2022 | — | Open |
| cwa | Schedule Event achieved late but reported | Mar 31, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2022 | May 12, 2022 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 31, 2022 | May 12, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 31, 2022 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 31, 2022 | May 12, 2022 | Resolved |
| cwa | Schedule Event reported late | Mar 31, 2022 | — | Open |
| cwa | Schedule Event reported late | Mar 31, 2022 | — | Open |
| cwa | Schedule Event unachieved but reported | Mar 31, 2022 | May 6, 2022 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2022 | May 6, 2022 | Resolved |
| cwa | Schedule Event achieved late but reported | Mar 31, 2022 | — | Open |
| cwa | Schedule Event reported late | Mar 31, 2022 | — | Open |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2022 | May 12, 2022 | Resolved |
| cwa | Schedule Event unachieved but reported | Mar 31, 2022 | May 6, 2022 | Resolved |
| cwa | Schedule Event unachieved and not reported | Mar 31, 2022 | May 6, 2022 | Resolved |
| cwa | Schedule Event reported late | Oct 31, 2021 | — | Open |
| cwa | Schedule Event achieved late but reported | Oct 31, 2021 | — | Open |
| cwa | Schedule Event unachieved and not reported | Oct 31, 2021 | Jun 27, 2022 | Resolved |
Discharge Limit Exceedances
Instances where this facility's reported discharge monitoring results exceeded its permitted limits under the Clean Water Act. Exceedance percentage shows how far over the permit limit the discharge was.
| Pollutant | Violation | Reported | Limit | Exceedance | Period | Status |
|---|---|---|---|---|---|---|
| Solids, total suspended | DMR, Limited - Numeric Violation | 11.00 mg/L | 8.30 | +33% | Nov 2018 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 292.00 MPN/100mL | 200.00 | +46% | May 2018 | Open |
| Coliform, fecal general | DMR, Limited - Numeric Violation | 159.80 MPN/100mL | 100.00 | +60% | May 2018 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 10.00 mg/L | 8.30 | +20% | Apr 2016 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 10.00 mg/L | 8.30 | +20% | Feb 2016 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 17.00 mg/L | 8.30 | +105% | Nov 2015 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 17.00 mg/L | 8.30 | +105% | Oct 2015 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 16.00 mg/L | 8.30 | +93% | Mar 2015 | Open |
| Solids, total suspended | DMR, Limited - Numeric Violation | 16.00 mg/L | 8.30 | +93% | Feb 2015 | Open |